...
Release Schedule
Revision: r7 r10
Activity Log
Date | Rev | Event or Update | Milestones Affected |
---|---|---|---|
06/30/22 | r10 | The open items from the previous week were reviewed with the TSC. All had been resolved or deferred to the next release. The TSC approved Sign Off by vote. | Sign Off |
06/27/22 | r10 | The remaining open items were reviewed during the PTL meeting. Most were resolved or deferred to Kohn. Some actions were assigned to clean up some minor items. There were an insufficient number of TSC members on the PTL call, so the decision was made to defer the vote on sign off to the TSC meeting on June 30. | Sign Off |
06/23/22 | r10 | TSC determined that the release was not ready and pushed sign off to June 27. | Sign Off |
06/09/22 | r10 | TSC determined that the release was not ready and pushed sign off to June 23. | Sign Off |
06/02/22 | r9 | TSC determined that the release was not ready and pushed Sign Off to June 9. | Sign Off |
04/28/22 | r8 | TSC pushed RC to May 12 and Sign off to June 2. Also added Ascension Day holiday on May 26 | RC, Sign Off |
03/31/22 | r7 | TSC conditionally approved M4 | M4 |
03/24/22 | r7 | TSC rescheduled M4 to Mar 31 due to lack of progress on M4 milestone tasks, as well as M3 tasks that were excepted on Mar 10. No other milestones affected. | M4 |
03/10/22 | r6 | TSC approved M3 on the condition that remaining release management tasks be completed by M4. See TSC meeting minutes for details. | M3 |
03/03/22 | r6 | Removed erroneous event | None |
03/03/22 | r5 | TSC agreed to slip remaining schedule, beginning at M3, by one week. Also updated schedule to include DTF workshop in March. | M3, M4, RC, Sign Off |
02/03/22 | r4 | TSC conditionally approved M2. Details here: https://wikilf-onap.onapatlassian.orgnet/wiki/x/paEEBwxzzs. | M2 |
01/27/22 | r4 | TSC approved 1 week slip to M2. Remainder of schedule is unchanged. | M2 |
12/02/21 | r3 | TSC approved 1 week slip to M1. Remainder of schedule is unchanged. | M1 |
11/28/21 | r2 | Corrected dates for Dev & Test Forum | None |
10/28/21 | r1 | TSC approved the Jakarta schedule | All |
10/25/21 | r1 | Added continuous delivery view to the schedule, per the working group feedback and PTL meeting review. | All |
09/30/21 | TSC approved schedule Note: milestone dates are approved, but there is interest in the community to change the appearance of the schedule to better communicate the agile aspect of the release process. Magnus and Ciaran have launched a working group to develop a proposal for the TSC. Therefore, although the dates are approved, the schedule remains "draft". | All | |
09/15/21 | First draft posted | All |
...