The content of this template is expected to be fill out for M1 Release Planning Milestone.
...
Project Name | Enter the name of the project |
---|---|
Target Release Name | Guilin |
Project Lifecycle State | Incubation. Refer to ONAP Charter, section 3.3 Project Lifecycle for further information |
Participating Company | AT&T, ZTE |
...
The scope of the Guilin Release of ESR will address Vulnerability Security Fix and Platform Maturity Requirements, as well the approved use cases.
Highest priority will be assigned to support security and platform maturity requirements. As next highest priority, ESR will support the approved use cases. Best-effort additional development will continue to support additional features not included in the approved use cases.
ESR R7 Guilin Release: Other requirements
Requirements
Minimum Viable Product
...
Key | Summary | T | Created | Updated | Due | Assignee | Reporter | P | Status | Resolution |
---|---|---|---|---|---|---|---|---|---|---|
AAI-2888 | Upversion to DropWizard V2.0.2 | Apr 29, 2020 | Apr 29, 2020 | Peng He | Peng He | 开放 | 未解决 | |||
AAI-2889 | Java 11 support | Apr 29, 2020 | Apr 29, 2020 | Peng He | Peng He | 开放 | 未解决 | |||
AAI-2890 | ESR Guilin Document | Apr 29, 2020 | Apr 29, 2020 | Peng He | Peng He | 开放 | 未解决 | |||
AAI-2891 | Kubernetes based Cloud regions Support | Apr 29, 2020 | Apr 29, 2020 | Peng He | Peng He | 开放 | 未解决 |
...
Stories
Key | Summary | T | Created | Updated | Due | Assignee | Reporter | P | Status | Resolution |
---|---|---|---|---|---|---|---|---|---|---|
AAI-2847 | Added NFVO GUI internationalization file | Mar 30, 2020 | Apr 29, 2020 | Peng He | Peng He | 已关闭 | 完成 | |||
AAI-2856 | Remove JQuery 1.11.0 from ESR Version | Apr 07, 2020 | Apr 29, 2020 | Peng He | Peng He | 已关闭 | 完成 | |||
AAI-2857 | Upgrade to Apache Tomcat 9.0.31 | Apr 08, 2020 | Apr 29, 2020 | Peng He | Peng He | 已关闭 | 完成 | |||
AAI-2858 | Remove BootStrap 3.1.1 from ESR GUI | Apr 08, 2020 | Apr 29, 2020 | Peng He | Peng He | 已关闭 | 完成 | |||
AAI-2859 | Upgrade to bootbox 5.4.0 | Apr 08, 2020 | Apr 29, 2020 | Peng He | Peng He | 已关闭 | 完成 | |||
AAI-2876 | Upversion to MSB-JAVA-JDK 1.2.5 | Apr 22, 2020 | Apr 29, 2020 | Peng He | Peng He | 已关闭 | 完成 | |||
AAI-2863 | Integrating aai-parent as the parent pom | Apr 13, 2020 | Apr 29, 2020 | Peng He | Peng He | 开放 | 未解决 | |||
AAI-2892 | Change MSB Server Port in Test Case Code and Test it | Apr 29, 2020 | Apr 29, 2020 | Peng He | Peng He | 开放 | 未解决 | |||
AAI-2895 | Resolve Esr-gui Root Running | Apr 30, 2020 | Apr 30, 2020 | Peng He | Peng He | 开放 | 未解决 | |||
AAI-2896 | Resolve Esr-server Root Running | Apr 30, 2020 | Apr 30, 2020 | Peng He | Peng He | 开放 | 未解决 |
Longer term roadmap
- Focusing on security and reducing turn around on 3rd party dependency vulnerabilities
- Enhanced UI of ESR GUI
...
Indicate where your project fit within the ONAP Architecture diagram.
Block and sequence diagrams showing relation within the project as well as relation with external components are expected.
...
List the API this project is expecting from other projects.
Prior to Release Planning review, Team Leads must agreed on the date by which the API will be fully defined. The API Delivery date must not be later than the release API Freeze date.
Prior to the delivery date, it is a good practice to organize an API review with the API consumers.
...
Name | Description | Version |
---|---|---|
BootStrap | Popular framework for building responsive and a template starter page | 4.3.1 |
JQuery | Open-source JavaScript Library | 3.4.1 |
Docker | VM container | |
DropWizard | Open-source Microservice application Java Framework | 1.3.0 or 2.0.2 |
Apache Tomcat | Open-source implementation of the Java Servlet | 9.0.33 |
Jersey | Open-source RESTful Web Services framework | 2.16 |
Jetty | Servlet Engine and Http Server | 9.4.22 |
...
Please update any risk on the centralized wiki page - Frankfurt Riskspage
Resources
Fill out the Resources Committed to the Release centralized page.
Release Milestone
The milestones are defined at the Release Level and all the supporting project agreed to comply with these dates.
...
Please update the following centralized wiki: Frankfurt Documentation
That includes
- Team contributions to the specific document related to he project (Config guide, installation guide...).
- Team contributions to the overall Release Documentation and training asset
- High level list of documentation, training and tutorials necessary to understand the release capabilities, configuration and operation.
- Documentation includes items such as:
- Installation instructions
- Configuration instructions
- Developer guide
- End User guide
- Admin guide
- ...
...
Each project must edit its project table available at Project FOSS.
Charter Compliance
The project team comply with the ONAP Charter.