We will start our meetings by mentioning the project's Antitrust Policy, which you can find linked from the LF and project websites. The policy is important where multiple companies, including potential industry competitors, are participating in meetings. Please review and if you have any questions, please contact your company legal counsel. Members of the LF may contact Andrew Updegrove at the firm Gesmer Updegrove LLP, which provides legal counsel to the LF.

AttendedProxy (w/ @name)Gov. HolidayDid Not Attend

...

Agenda Items

Presented By

Presos/Notes/Links/

Release Status

Weekly status

  •  
    • Jira Legacy
      showSummaryfalse
      serverSystem Jira
      columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
      serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
      keyREQ-760
       - missing from Impact per view 
      • damian.nowak reports that there are no current issues with dual stack support, based on results of daily testing.
      • Note that REQ-718 (spec) and REQ-760 (GR) are different issues
      • Damian has added REQ-760 to the impact view page.  However, this is simply for completeness as there are no current issues.
      • Chaker Al-Hakim Chaker has updated ONAPARC-639 to include approval of REQ-760, based on review of other similar requirements
      • Next steps:
    • Jira Legacy
      showSummaryfalse
      serverSystem Jira
      columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
      serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
      keyVFC-1875
       - SECCOM opinion?
      • To be re-opened and added recommendation to use the integration base image (see Jira)
      • Suggestion that this should be proposed as a best practice REQ for Jakarta release
  • Honolulu Maintenance
    • Jira issues
    • Next step: Regression Tests by the Integration Team i.e. Healthcheck, Smoke Tests - Morgan Richomme waiting for OOM updates to initiate daily tests on Honolulu branch

RelEng/Infrastructure

  • Tickets- Open showstoppers:
    • Gerrit & Jenkins issues this AM
    • Issue was due to zombies resulting from Gerrit restart.
  • Tickets- Waiting on Community:
  • Migration Status / Upcoming Changes

Update on integration lab status

EU support 

RelEng/Infrastructure

#AGREED the TSC approves the OOM Gitlab POC using CLA validation via the ci chain demonstrated in https://gitlab.com/kopasiak/oom_cla_test/-/merge_requests/1 as a workaround until EasyCLA supports GitLab

LFN Cross-Organization Updates

MAC, SPC, TAC, EUAG, LFN Board

Update for the LFN Governing Board

  •  (Sunday preceding the ONE Summit)  GB meeting to include update preso from the LFN Project TSCs. 
  • Template will be provided shortly - GB asked for changes
  • 2022 budget process will be that same as in the past.

TSC Activities and Deadlines

ONAP Community Awards: Honolulu Release

TSC 2.0 Community Document Draft

Upcoming Events & Housekeeping

PTL meeting on Sept 6 is canceled due to the Labor Day holiday in the U.S.

...