Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

zoom bridge: https://zoom.us/j/283628617

Duration 60 minutes

DurationAgenda ItemRequested byNotes / Links
START RECORDING
30min

Dublin end game plans


RC2 - May 30th (Euro holiday)

Sign-off - June 6th

RC1 Follow-up: Deliverables for RCx Milestone Checklist Template

!!! PTLs to provide latest RELEASE Images ASAP, especially if you made changes post-RC0 !!!

  • #75479: Release of OOF RC0 artifacts
  • #75986: Please release SO libs artifacts


  • Pair-wise testing still in progress for Policy (91%), Portal (67%) and SO (89%) teams
  • Test Coverage Waivers for AAF, Multi-Cloud and SDC are in progress but as per today,

Please provide your RC2 checklist no later than May 29th 11am PST- thank you

10minCII badging and vulnerability disclosure

Call to action: Update you CII badging info

Pawel created a ticket to improve readthedoc, working with Sofia accordingly

(SECCOM): provide template for PTLs to report their security/vulnerability issues including rules for exposing ports outside the cluster

#2 CII badging - e-mail sent to PTLs & Security

#2.1 SO is ok to be reviewed by Security

#2.2. another few projects still need to complete their items

10 minEl Alto security prioritiesPaweł Pawlak

Key components versioning, recommendations after known vulnerabilities analysis, follow-up with fixes related to OJSI tickets, ONAP communication matrix

#3.1 Work in progress. Natacha is working on a proposition to be presented during ONAP DDF in Sweden

Additional recommendations from Security about K8S, Tomcat, Alpine, etc. should be defined for the incoming releases so each project will have a common OS, common open source strategy

#3.2 OSJI tickets - interaction with PTLs is required - Please have a look at them asap

Holmes, Logging, Portal, UUI, VFC, VNFSDK - vulnerability table

OOM - CII Badging - now updated

#3.3 Other item:

Early disclosure to Operators has been approved by TSC. In the future, audience could be reviewed - SECCOM to assess

Any WednesdayTUESDAY, feel free to join SECCOM if you have any suggestion

...

@Pawel, CII badging updated for OOM

Action Items

  •  2/11: Migrate Docker image releases from Nexus3 into Docker Hub (Architecture Independence) by Dublin M4. 
    <2-15-2019> Preparing a preso for review of all known infrastructure change requests for review at PTL meeting 2-25-2019
    <2019-04-08: global-jjb progress report: start on DCAE soon - focus on El Alto delivery (precursor to Dockerhub)<2019-04-22 - Using mvn staging plugins to deploy - unfort many of the changes need to be in the source code to insure the job is running><2019-05-27> global-jjb still in progress
  •  Tlab persistent storage IO architecture Rich Bennett 
    Request from Rich Bennett about Storage/Persistent Data Architecture Plan/PTLs - Single NFS server? 
    <2019-04-22: performance issues with old config - have bare metal cluster - - want to bring in more realistic operational aspects to the testing - network storage vs direct, would like to place modules in isolation into the environment. Evaluating the utility of testing this way.