...
- TSC agrees to cancel the TSC Call on November 1st, 2018
- TSC agreed to proceed without "5G PNF Live Mngt Support" excluding steps 36/37 (TSC-26)
- TSC approved the ONAP Release Manager RC1 recommendations i.e. Grant RC1 to16 out of 30 projects.Conditional on all other Projects in addressing Orange and Red Items by Oct 31st, 2018
https://wiki.onap.org/download/attachments/45296866/ONAP%20Casablanca%20RC1%20Status%20Summary%20Oct25Version1.pdf?version=1&modificationDate=1540553903000&api=v2
November
11/08
- TSC agrees to cancel the TSC Call on November 22nd, 2018
- TSC agrees to shift the Casablanca RC2 (Nov 8th → Nov 27th); Casablanca Sign-off (Nov 15th → 30th); Plan an extra-Ordinary Casablanca Release Maintenance on Jan 31st, 2019 including any use case not passing RC2 milestone criteria
...
- TSC agrees that Alexis de Talhouët will take over from David S (BELL TSC reserved seat). Alexis was previously acting as BELL TSC deputy.
11/29
- TSC approves RC2 Casablanca Release Milestone
- TSC approves Casablanca Release Sign-Off on Nov. 30 with the Press Release at 9 AM Pacific, Dec. 4th, 2018
December
12/6
- TSC agrees to cancel the TSC Call on December 27th, 2018
- TSC votes on 2019 Budget Reductions Action