Release Schedule

Revision:  r2

Image Removed

Activity Log

...

 

...

Reviewed draft schedule with the TSC.  TSC approved the schedule.

...

 

...

Shared draft schedule with PTL meeting.  No objections or other feedback.

...

 

...

Uploaded a proposed schedule for New Delhi using the guidelines for scheduling for the new release process (see note for Sept 7, below).

...

 

...

The TSC approved a new release process, following several weeks of discussions and meetings.  The new release process greatly simplifies the release process and release schedule, including eliminating milestones.  The only events on the schedule for the new process will be Kickoff, Release Candidate (RC), and Sign Off.

...

 

...

The TSC approved a proposal to push M1 out by two weeks to avoid conflicting with the updated London schedule.

Also added D&TF event and updated date for London Sign Off.

...

 

...

 

...

Met with ODL to review New Delhi schedule.  The draft schedule appears to be a good fit for projected ODL release activities.  The plan is to integrate the ODL Argon release. 

No updates to the New Delhi draft required.

...

 

...

Image Added

India Gate in New Delhi, March 20, 2016 (Credit: A. Savin, WikiCommons)

Release Schedule


RC : May 16 → May 23

Sign off: June 6 → June 13


Gliffy
macroId21352d9d-4253-4925-97e2-2d02993f185b
displayNameNew Delhi - Oslo release schedule
nameNew Delhi - Oslo release schedule
pageid16550130


Image Added

Activity Log

DateRevEvent or Update


Initial draft posted


#Agree: TSC agrees to proposed release planning schedule for New Delhi