Release Schedule r4
Change Log
Date | Event or Update | Milestones Affected |
---|---|---|
June 24 | Initial version of schedule approved by TSC by mail vote. | N/A |
July 9 | M1 milestone requirements not met. TSC agrees to slip M1 to July 13. | M1 |
July 13 | M1 milestone requirements not met. M1 slips to July 16. | M1 |
July 16 | Project milestone status 100%, but requirements still not resolved. M1 slips to July 23. | M1 |
July 23 | TSC approved M1 (2 week slip from original plan) | M1 |
August 6 | M2/3 milestone reqirements not met. M2/3 slips to August 11 | M2/3 |
August 13 | TSC approved M2/3 with conditions | M2/3 |
September 10 | TSC agrees that M4 milestone requirements not met. Agrees to review again on Sept 17. | M4 |
September 17 | TSC approves M4 with exceptions | M4 |
September 18 | Propose moving RC0 to Oct 12, and remaining milestones move out by 1 week (sign off, Nov 12). | RC0, RC1, RC2, Sign-off |
September 24 | TSC approved moving RC0 to Oct 12, and remaining milestones out by 1 week | RC0, RC1, RC2, Sign-off |
October 12 | RC0 requirements not met | RC0 |
October 19 | RC0 requirements not met | RC0 |
October 22 | Proposal: Move RC1 to Nov 5 Move RC2 to Nov 19 and combine with Sign-Off | RC1, RC2, Sign-Off |
October 22 | RC0 approved with caveat that war room continue to resolve SO/OOM issues | RC0 |
October 22 | Schedule proposal approved | RC1, RC2, Sign-Off |
November 12 | TSC approved merging RC1 with RC2 and sign-off on Nov 19 | RC1, RC2, Sign-Off |
November 19 | RC1 / RC2 / Sign Off moved to Dec 3 | RC1, RC2, Sign-Off |