Objective

How Achieved

Participant Preparation required

Action items out

3

Review JIRA Backlog. Participants should be comfortable that they understand the backlog of tasks for our project ( 5 min)

Close Sprint 20

Walk through the JIRA backlog to check for completeness


review:  docs.onap.org ( latest)

vnf guidelines open gerritt

vnf requirments open gerritt

vnf test open gerrit

vnf use cases open gerritt

vnfrqts bugs


4

Develop Next Sprint Participants should be comfortable with an achievable development sprint scope ( 30 min)

Start Sprint 21

Walk through the JIRA backlog





5Relationships with other projects (10 min)review project handoffs

review handoffs with

DOCS

VVP

VNF SDK

Modelling

LFN C&V

others?

create any necessary User Stories


Release Planning: Dublin:

RC0: May 2, 2019

RC1: May 09, 2019

RC2: May 23, 2019

Signoff: May 30, 2019

El Alto

Frankfurt



 

Candidate VNFRQTS work items for Dublin 


 update Project Release Plan & Release EPICs

   7. Any other Business? (5 min) 

Test case Description / framework for testing live VNF instances:

  • third party test labs must be able to run test cases and generate reports for VNF certification
  • operators must be able to run test cases against VNFs that have been onboarded.
  • needs to be decided and documented before end of El Alto
  • blocks VNF test case development



Meeting Notes