This template must be filled out for every Release Candidate Milestone (RC0, 1, 2, x)

RC Release Candidate Milestone overview is available in wiki.



For RC0, for project delivering binaries, has the team populated and validated all the sections of either the Platform Component or SDK template?

Practice AreaCheckpointYes/NoEvidencesHow to?
Product ManagementAre all tasks associated with the release been marked as "Closed" in Jira?Yes

Jira Legacy
serverSystem Jira
jqlQueryproject=clamp and type=Task and fixversion="Casablanca Release"
counttrue
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176



Have all findings from previous milestones been addressed?YesN/A
DevelopmentHave all Defects of priority Highest and High been in status "Closed" in Jira?Yes

Jira Legacy
serverSystem Jira
jqlQueryproject = Clamp and (priority = high or priority = highest) and status = open
counttrue
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176


Are all JIRA issues used as a reference in a commit in status "Closed" in Jira?Yes

Is there any pending commit related to Highest and High priority issues older than 36 hours in Gerrit? In case there are messages going back and forth between authors and reviewers, it is acceptable to be above 36 hours.No

Are all the Jenkins jobs successfully passed (verify + merge jobs)?YesCLAMP jenkins tab

Has the team delivered all their release artifacts in Nexus Release repo?

There should be at least ONE version of each artifacts available in Nexus Release repo.

Yesclamp NexusRefer to Independent Versioning and Release Process for procedure
Integration and TestingHave all CSIT Use Cases (created by each project team) passed?YesJenkins CLAMP tab
At RC0RC1, has the Pair Wise testing table been filled out?YesCasablanca Pair Wise Testing master pageThe OOM pairwise testing has been finalized(all tests passed) on the 19th of October
At RC0RC1, have all OOM Release Healtcheck related to your project passed?Yes

At RC0RC1, is there a Docker image in Nexus Docker-Release repo available for each repository?YesNexus 3 clamp docker repo
Has the project code successfully passed the Daily Build process?YesJenkins CLAMP tabGoal is to ensure the latest project commit has not broken the Integration Daily Build 
Has the OOM deployment passed?YesEnsure in Jenkins External Labs all Health Check pass.

Has the Heat deployment passed?

(not a gating item for Casablanca)

YesEnsure in Jenkins External Labs all Health Check pass.
DocumentationYes

Most teams have already created the high level file structures in readthedocs, and populated some actual documentation. However, the remaining sections of the appropriate teamplate must be completed.

Platform: A&AI, APP-C, CLAMP, CLI, DCAE, DMaaP, Holmes, MSB, OOM, Policy, Portal, SDN-C SDC, SO, UseCase UI, VFC, VID

SDKs: AAF, CCSDK, External API Framework, Multi VIM/Cloud, VNFSDK

  Documentation  

For RC1, has the team addressed any issue (recorded in JIRA) provided by the Documentation team?

 Yes 