Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

  1. Presentation on Change Management progress from ATT.
    1. Eliane Elain presented the Change Mgmt feature and feature 
    2. addressed the queries

  2. Details and planning for M4 tasks and sprints
    1. Stories are planned for the sprint 
    2. Consensus was brought in for handling  the planned stories

  3. CCVPN new workflow for the Wan Service - By ZTE
    1. It was decided asked to have deeper analysis required on why the new WAN service CCVPN workflow is needed and if the exiting workflows could be sufficient to hadlehandle
    2. This feature would require changes across ONAP and hence needs conclusive approval from components involved.


Next week agenda:

  • Presentation on Workflow designer -  SDC progress from ATT.
    Details and planning for M4 tasks and sprints