The following items are expected to be completed for the project to Pass the M3 API Freeze Milestone.

M3 Release Architecture Milestone overview is available in wiki.

Info
titleUsage
  1. Use the "Copy" and "Move" options (available under the ..., top right of this page) to duplicate this template into your project wiki.
  2. Fill out the Yes/No column
  3. Provide link to evidence (when necessary)
Practice AreaCheckpointYes/NoEvidencesHow to?
Architecture


Has the Project team reviewed the APIs with the Architecture Committee (ARC)?

Planned

For Tuesday 31

Documen:

Arch slides


Architecture walkthrough to understand how each project contributes on Release Use Case. ARC to organize the walkthrough.

Is there a plan to address the findings the API review?
Link to plan
NA
The plan could be as simple as a Jira issue to track the implementation of findings or a documented plan within the wiki.
Does the team clearly understand that no changes in the API definition is allowed without formal TSC review and approval?
NA
YES
In the case some changes are necessary, bring the request to the TSC for review and approval.

Is there any changes in the scope, functionalities, deliverable, dependency, resources, API, repositories since M1 milestone?

If Yes, please a link to the evidence of these changes.
NO
Critical point to understand is that change is inevitable, and that right timing and clear communication to the community will ease the process of accepting changes.
Provide link to the API Documentation.YES

API Design document & swagger are available

API Listener swagger

API ServiceOrder swagger

Design document


Release ManagementAre committed Sprint Backlog Stories been marked as "Done" in Jira board?
Provide Link to Project backlog
YES

All 6 stories are done

Link to stories in JIRA


Are all tasks associated with Sprint Backlog Stories been marked as "Done" in Jira?NA

Have all findings from previous milestones been addressed?NAProvide link to JIRA findings
DevelopmentIs there any pending commit request older than 36 Business hours in Gerrit?NO

Do you have a plan to address by M4 the Critical  and High vulnerabilities in the third party libraries used within your project?YES

Jira Legacy
serverSystem Jira
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
keyEXTAPI-126

Ensure by M4 the Nexus-IQ report from “Jenkins CLM” shows 0 critical security vulnerability. Open the Nexus-IQ report for the details on each repo.

Are all the Jenkins jobs successfully passed ( Merge-Jobs)?

Provide link to evidence

YES

Jenkins externalapi

Git externalapi/nbi

Sonar line coverage: 69%

https://sonar.onap.org/dashboard?id=org.onap.externalapi-nbi%3Anbi-rest-services


Are all binaries available in Nexus?
Provide link to evidence

JAR in nexus

Docker in nexus


Integration and Testing

Have 50 % of System Integration Testing Use Cases been implemented successfully in Jenkins?

Provide link to evidence
NANo integration test
Has the project code successfully passed the Daily Build process?YES

Both java an docker daily build

https://jenkins.onap.org/view/externalapi/

Goal is to ensure the latest project commit has not broken the Integration Daily Build 


https://wiki.onap.org/display/DW/calendars