...
Chris Lott, Lorraine Welch, Weiting, Leimeng Shi, Sunder Tattavarada, MULLICK, GARIMA, Farhan Mir
Discussion Items:
- Went over JIRA list and re-prioritized items
- Extend Portal-119 to split DB for Portal and SDK - Chris
- Sent grep scan on "master_dev" branch to check if "ecomp" appears in Portal - Lorraine
- SDK will be next to scan - Lorraineready
- Sent email to announce SDK is ecomp free for partners to use - Leimeng will send email outSonar coverage to partners about SDK 1.3.2 - Leimeng
- Split Portal-19 to Jima and Robert (based on Lorraine's scan output)
- JUnit /Sonar coverage to 50%, assigned to HimaEnter EPIC/Stories for Beijing M1 planning
- Discussed remaining JIRA items in great details
- Beijing Release Planning:
- M0 - dev kick-off, Nov 16
- M1 - planning Jan 16
- M2 - functionality freeze Feb 15
- M3 - API freeze Mar 1
- M4 - code freeze Apr 5
...