AGENDA
Duration | Agenda Item | Requested by | Notes / Links |
---|---|---|---|
START RECORDING | |||
Dublin logistics | |||
Policy Scrum Status | Pamela Dragosh | ||
CLAMP Update | |||
ATTENDEES
Samuli Silvius - Samsung
Ninoo Panda
Daher
Devendra
Josh
NOTES
- Dublin Logistics
- Finish stabilization of components
- Finish CSIT
- Pairwise testing must be done by RC0
- Highest Bugs that block Integration must be addressed first
- Documentation done by RC2
- Saravanan Ayyadurai - lab issues will start testing SDNR when resolved
- vidyashree.rama - will start testing CCVPN
- Suggestion is to have a meeting with community regarding the Policy JIRA Backlog
- Mid-May is target
- Policy Scrum
- CLAMP update
- Stabilizing and fixing some bugs
- DCAE pairwise testing - talk with Vijay on that
- Checkstyle commit