IssueNotesDecision
1CPS to deliver java-interface only

This affects our Wow in many aspects.

  1. Requirements on Java interface instead of REST
    1. REST first or Java first, parallel?
  2. How to Test & Demo in CPS Team

 

Csaba Kocsis  proposed that CPS Team will deliver Java impl. first and then E// will take our code and wrap and a REST interface around it.

Toine Siebelink CPS team will work out during Grooming how to demo withour REST interface, most like using Groovy (semi) Integartion Tests. Daniel Hanrahan his about to complete a test framework for test NCMP services.


2Validation in REST or Java Service

Balance between early validation and common code

Continue with current process. Review case by case Toine Siebelink  Csaba Kocsis  


3Why is NCMP forwarding the response, DMI could do this ?Involve extra performance cost from CPS 

  Implementation needed because of TBAC 


4Are Java doc expected to be publishedYes. Agreed to deliver as a separate artefact (Shall be versioned ... where should it go ?)

Versioning of the interface shall be the same as the service delivered by CPS. New v should not affect the interface, version numbers could change and shall be documented  


5Delivery artefacts

Required Artefacts

  1. JavaDoc for new interface
  2. Jar(s ?) for services support new interface

  AP to confirm with Andreas in team Lightening

 Csaba Kocsis to revert


6Characteristics

Need to discuss priority of this. Delivering a functioning MVP for EPIC is important. Discussion and agreement with Peter T needed

  Still needed, might not get response because the new team are yet to start any integration. AP Kolawole Adebisi-Adeolokun to get a decision from Peter/David 

 Csaba Kocsis  to revert


7Results - Why can't DMI send result after completion of job with be told to do soSimply less work if DMI can decide itself, no additional interface in other components needed to trigger this....
8Exact form of Alternate ID(s) FDNs

uri-FDN and  LDNs should contain "/" and not "," as delimiters at the start of the naming attribute

FDN example : 

Subnetwork=22,MeContext=Kista,ManagedElement=Kista,GNBDUFunction=1,UECC=1

URI FDN example : 

/Subnetwork=22/MeContext=Kista/ManagedElement=Kista/GNBDUFunction=1/UECC=1

Should be compliant with 3GPP, should start with '/ '  

https://github.com/jdegre/5GC_APIs/blob/Rel-18/TS28532_ProvMnS.yaml



Kieran Mccarthy A  Users are advised to use URI-FDNs for alternate IDs to minimize performance impacts of conversions etc.   Rafael Rocha  ALL  cps


9MVP (Minimum Viable Product) for DCM
  1. Expected Delivery to EIC  Q3(August) to EIC. (Fossing and Testing)

  2. Write Only Should be prioritized for target delivery (Q3). It should include
    - Batch write
    - NCMP should only check the cmhanlde of the first operation 
    - Should Databag be populated or not kieran mccarthy / Csaba Kocsis ?
  3. Also included is status and results endpoint
  4. NCMP should prioritize CPS-2009 Update remaining existing/legacy NCMP APIs to support alternate Id (FDN) - Developer Wiki - Confluence (onap.org) - over datajob Read. New Epic to be created for DataJob Read sperate this from 1964 - > CPS-2189
  1. EIC Expected Delivery  Q3(August)

10DataJob Read v Write prioritizationWrite should be prioritized over read


11Use of '/ ' causes some issuesNot at issue. FDN can support / and ,


12

Prioritize CPS-2009 Update remaining existing/legacy NCMP APIs to support alternate Id (FDN) - Developer Wiki - Confluence (onap.org) - over Read.

New Epic requested for DataJob Read sperate this from 1964.

Expected even earlier than q3

Agreed to move higher on R14 - #17


13

NCMP still need to convert Legacy Event to Cloud Event before we can Update the Legacy APIs to support AlternateId

Currently ETH are only consuming the LCM event and we agreed shall remain Legacy event for MVP delivery.

Kolawole Adebisi-Adeolokun Peter Turcsanyi Csaba Kocsis


14

Decision to add status & result as part of this MVP


No new epic required for write, maintain current priority, wrap up this epic with;

  1. Status - (Finished/Ongoing)
  2. Result - (Success/Failure)



15Is the requestId in the southbound request equal to the dataJobId coming in from the northound interfaces? (see writeJob for example)
Can the dataJobId used as the requestId?

Kolawole Adebisi-Adeolokun confirmed dataJobId can be used as the requestId


16

Define & agree on a Java interface (do we need a different method for write) The output should be defined

 We need a clarification on the response.

Kolawole Adebisi-Adeolokun // The output is currently being define by team Lighting AP @ko to follow-up


...

AP Kolawole Adebisi-Adeolokun  To follow-up and check the possibility of merging this with the read & write the read & write or just keeping the error sci. separate as is;

High Level Solution




Gliffy
macroIdd1631b9a-be48-4bc6-96b7-364b3cf77464
nameAsync_Datajob
pagePin1

...

  • Conflict management, DATAJOBS are BATCH OPERATION.


PO Comment

-CPS will need to leave epic open, @kola Kolawole Adebisi-Adeolokun to organise a sync with team lighting Lightning on their current progress

-dev wise, CPS has fulfilled all functional aspect of this epic but can't progress in further because the interface isn't ready yet from Team Lightning

-Should we CPS consider demo ? - Kolawole Adebisi-Adeolokun  to Check with team lighting if Lightning when we could can arrange a demo upon a demo working interface