Table of Contents |
---|
Key Contacts - Byung-Woo Jun (Ericsson)
Release Plan Overview
- Marketing version, Montreal, will be scheduled as the previous releases, with following changes (see next two pages for more details)
- Setting release schedule plans for Montreal with Start / RC / Sign off dates only
- The Marketing version will be used as the Major version by ONAP projects
- PTLs decide the minor and patch versions, based on their project release cycles and share the project versioning with TSC
- provide each project release flexibility and evolution
- Integration & Pair-wise testing
- Integration testing will continue to increase ONAP project overall qualities
- Pair-wise testing will continue but it will be based on use cases
- Project testing will be performed by each project team
- For Montreal, security scanning will continue as before
- Based on feedback during the Montreal, the release plan can be revisited
...
- Review, approve and determine overall ONAP proposals and directions
References
- ONAP Streamlining - The Process, Release Plan for TSC approval, at https://jira.onap.org/secure/attachment/18969/ONAP%20-%20Streamlining%20the%20process%20Report-2023-9-7-v1.pptx (see pages 13, 14 and 15 for release plans)