Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

DateRevEvent or UpdateMilestones Affected
01/19/23r3The TSC approved the M1 milestone, with the exception of OOF and AAI (currently lacking PTLs, so they are unable to complete RM tasks)M1
01/05/23r3The TSC approved the schedule proposal.M1, M2, M3, M4, Sign Off
01/04/23r3The entire schedule (M1 - Sign Off) has been updated, per request of the TSC on Dec 15, due to ongoing issues in completing M1.  TSC to review this proposal on Jan 5.M1, M2, M3, M4, Sign Off
12/08/22r2The TSC rescheduled M1 to Dec 15 due to lack of progress on release management tasks.M1
11/10/22r1The TSC slipped the date for Kohn Sign Off to Dec 1.  To prevent the Kohn and London schedules from overlapping, the TSC agreed to push out M1 by one week.M1
09/22/22
Schedule proposal approved by the TSCAll
09/15/22
First draft postedAll

...