This centralized page, for all Kohn projects, is aimed at identifying the risks as they are foreseen within the release life cycle.

A Risk that materialized becomes an Issue.

Status:

  • Identified: a risk that has been identified, but has not yet been analyzed / assessed yet 
  • Assessed: an identified risk which currently has no risk response plan 
  • Planned: an identified risk with a risk response plan
  • In-Process: a risk where the risk response is being executed 
  • Closed: a risk that occurred and is transferred to an issue or the risk was solved/avoided
  • Not occurred: a risk that was identified but that did not occur 
  • Rejected: created and kept for tracking purposes but considered not to be used yet


Risk IDProject Team or person identifying the riskIdentification DateRisk (Description and potential impact)Team or component impacted by the risk

Mitigation Plan

(Action to prevent the risk to materialize)


Contingency Plan - Response Plan

(Action in case of the risk materialized)

Probability of occurrence (probability of the risk materialized)

High/Medium/Low

Impact

High/Medium/Low

StatusNotes
1CPS

 

Scope creep in work item #1 (state handling) (CPS R11 Release Planning#CPS-CORE/CPS-NCMPRequirements) corresponds to a delay in other work items such as #4 (reading data (single CM handle, synchronous only)CPSBetter up front analysis of requirements and breakdown of jiras Move some tasks to future work items to ensure timely finish of work itemHighMediumIdentified