Jakarta Release timeplan |
M1 (Global requirement freeze) scheduled for 2nd December
Tasks for M1:
M1 postponed by 1 week from 2nd to 9th Dec. Other milestones unaffected We should plan to release more often in Jakarta to move towards a more CI way of working.
M1 approved by TSC
M2 milestone scheduled for 27th January
First delivery for Jakarta (1.10.0) built and submitted to OOM (https://gerrit.onap.org/r/c/oom/+/126602). Content can be seen here: https://docs.onap.org/projects/onap-sdc/en/latest/release-notes.html#version-1-10-0 Still in review in OOM 1.10.1 built and submitted to OOM (https://gerrit.onap.org/r/c/oom/+/127003) M2 passed last Thursday 3rd Feb. Next milestone is M3 on 3rd March
M3 planned for Thursday week 3rd March - last date for merging in functional changes for Jakarta. Code Coverage currently at 55.6% - must maintain above 55%
1.10.1 merged in to OOM M3 this Thursday 3rd Mar
M3 approved last Thursday. No new functionality can be added to Jakarta, only big fixes, documentation etc. M4 planned for 24th March
1.10.2 images built, but bug fixes merged in since, will create new version including bug fixes for inclusion in OOM
M4 postponed to this Thursday 30th March, other milestones not affected OOM review: SDC: https://gerrit.onap.org/r/c/oom/+/128003 SDC-WFD: https://gerrit.onap.org/r/c/oom/+/127872
M4 approved by TSC last Thursday, RC planned for 28th April OOM reviews continuing
OOM reviews for SDC and SDC-WFD merged. RC planned for Thursday
RC approved last Thursday, Sign off scheduled for 2nd June Bug raised on SDC for non-ssl port in sdc-fe - SDC-3954, need to fix or request a waiver
Non-ssl port issue addressed by: https://gerrit.onap.org/r/c/oom/+/129212
Sign off this Thursday 2nd June. Release management tasks for SDC completed:
Sign off moved to 23rd June
Jakarta sign off approved by the Technical Steering Committee on | |||||||||||||||||||||||||||||||||||||||||||||||||||||
Kohn timeplan |
Kohn timeplan has been approved by TSC. M0 was last Thursday 7th Apr
Kohn timeplan to be revised due to changes in Jakarta timeplan and holiday in some countries on 6th May . M1 (General requirement approved) proposed to be moved from 26th May to 9th June, M2 proposed to be moved to 30th June
Release plan updated: Release Planning: Kohn M1 moved to 9th June. Release management tasks published:
M2 moved to 14th July
M1 moved to 23rd June. M2 moved to 14th July | |||||||||||||||||||||||||||||||||||||||||||||||||||||
Kohn Impacts |
| |||||||||||||||||||||||||||||||||||||||||||||||||||||
Bugs | Open bugs: 40 39 (up down from 3640)
|
...