...
Release Schedule
Revision: initial approved schedule r1 proposal (not yet approved)
Activity Log
Date | Rev | Event or Update | Milestones Affected |
---|---|---|---|
05/19/22 | r1 | Identified a conflict between M1 and Ascension Day on May 26, due to Ascension Day not being on the original schedule. Proposed moving M1 to June 9 and M2 to June 30. Need to review with PTLs and then vote in TSC on June 2. Added Ascension Day. | M1, M2 |
03/31/22 | initial approved | TSC approved Kohn schedule | All |
03/10/22 | First draft posted | All |
...