Meeting Minutes - 3/3/2021 

...

  • Trudy Morgan : Present first ONAP/OPS-5G use cases 
    • 5 year effort - all work being done in the LF. Work will be up-stream w/o forking code
    • NIWC: Naval Information Warfare Center 
    • Research project - all work is unclassified.
    • Deck presented today: OPS 5G Use Case.pdf 

...

#1 Create a dedicated controller via SDNC and handle Magma GW like any other device

#2 Have an adapter for the magma in ONAP Service Orchestrator and use it as a resource orchestrator for the specific jobs.   Disadvantage: create something specific

#3 5G PNF Plug & Play and consider Magma GW as a PNF?

    Current proposal: Avoid to create something specific but re-use what it is already developed in ONAP (SO/SDNC/SDNR) and orchestrate directly the Magma GW via gRPC

...

#4 Can we conclude Magma is an EMS (Element Management System)? YES

#5 5G Blueprint based on Guilin/Honolulu? Magma release is scheduled by June 2021 therefore let's consider ONAP Honolulu release

...

  • Review of the integration with Magma Controller/GWs
    • Code updated for AWS environments and is how available.
    • Up and running with 2 deployments
    • fully containerized GW planned for v1.6 ( ~4 weeks out)
    • discussion this week and next should have sufficient content for the DTF
    • standard SDC/SO/Multicloud model  should be able to be used.
    • potential for SDNC or CDS might be able to be used later - TBD
    • Possibility of plug-n-play model to be used for AGW - something to look at
    • Installing the access GW automatically would be valuable
    • existing Magma baremetal upgrade model installs as a new package or collection of packages
    • For ONAP assumption of initial deployments are PNF and time permitting then on CNF
    • https://github.com/magma/magma/tree/master/experimental/cloudstrapper
    • Suggestion to have a meeting next week at the same time with a smaller group. (TAC conflict noted)
  • Information about Magma Security requirements @Arun Thulasi
  • DTF Event in June - 2021-06-DD - ONAP TSC Task Force: ONAP For Enterprise Business
    • Is the slot OK i.e. Tue Jun 8 2021, 16:30 - 17:30 CET/10.30am-11.30am EST?
    • Shall we meet on June 2nd, 2021 to finalize the DDF presentation?
    • ONAP For Enterprise call will be canceled on June 9th due to DDF event.

...

SO queries OOF for slice template selection and then slice instance selection. In response to slice instance selection query, OOF may return an existing slice instance or may recommend SO to create a new slice instance. A new process called Orchestration Task is created to manage recalibration of NSI&NSSI selection with manual intervention from the portal. A new SO adapter is created to be the adapter of NSSMF which will interact with external NSSMF for NSSI management. See the SO Impacts and Interfaces wiki page for details.

Meeting Minutes -  

...

  • ONAP/Magma KPIs Jorge Hernandez , Gervais-Martial Ngueko 
    • Can we be aligned with VES template? - to be validated with the Magma Team.
    • Determine the use cases, control loops that we can trigger out of Magma KPIs
    • Some options about Data Collection are still under evaluation including Prometheus (Apache 2.0 License)
    • How would we introduce Prometheus to ONAP? It is not specific for DCAE and could be used by other components
    • The main Prometheus server runs standalone and has no external dependencies.
    • The deployment of Prometheus requires some changes and ownership by the OOM Team
  • ONAP/SABRES Integration - waiting feedback from Dr. Eric Kline about the APIs (probably in November 2021) David McBride 
  • ONAP For Enterprise - Roadmap

...

  • ONAP/Magma KPIs discussions
    • VES (Virtual Event steam) specs discussion scheduled for the first 30 minutes of the Magma Bi-weekly Engineering Meeting
    • Welcome Shubham Tatvamasi, Vipin Rathi, Guillaume Belanger (Magma team)!
    • Jorge Hernandez , Gervais-Martial Ngueko , Vijay Kumar (ONAP DCAE PTL) - provide information about VES specifications and any useful material (VES KPIs samples, ONAP/Magma POC material/intial inputs, etc.) to the Magma team prior the meeting on Nov 18th, 2021.
    • Setup a pre-meeting with Shubham Tatvamasi to share ONAP/Magma POC material/intial inputs - will be defined over Magma 'slack channel' (Genral). Logistics support will be provided by David McBride , Kenny Paul  - thank you all !
  • ONAP/Magma Integration Updates (Service Delivery)? - Yogendra Pal, Lukasz Rajewski , Byung-Woo Jun
    • Yogendra Pal  - ONAP Honolulu release has been deployed to resume integration with Magma 1.6 (VNF/AGW - Access Gateway). Trying to deploy on Nov. 11th the Magma package through ONAP SDC (Service Design & Creation).
    • Lukasz Rajewski - Instantiation of Magma CNFs (K8S) - using ONAP SO CNF Adaptor (work in progress). Is there any plan concerning Magma CNF? Not yet part of the Magma roadmap.
    • No CDS Integration yet scheduled
  • Walmart's representative (Ciby)
    • Meeting scheduled tomorrow at 2pm PST
    • Purpose is to share the goals from the ONAP Enterprise Task Force, Onboarding Community process and later on, discuss any potential use cases
  • Sharing the presentation to Layer123 World Congress on Nov 17th, 2021

...

Meeting Minutes - @7:30 am PST

  • ONAP/Magma KPIs discussions - follow-up discussions on what we have learned from Nov 18th, 2021
    • Material/demos/slides were shared
    • No push back about using VES Specifications to collect KPIs from Magma but no agreement yet
    • 'ONAP' Slack channel with Magma has been created to kick-off the implementation
    • Next steps:
      • Magma Team to assess all the information shared on 11/18
      • Follow-up with Magma team early in january 2022 to determine - shall we code "VES" adaptor (accepted by 3GPP) in Magma code; will Magma do it? Need to agree with Magma about the next steps.
      • Additional discussions are required to define concrete use cases that we want to implement from ONAP side i.e. monitor Magma GWs, Network Slicing etc., without overlapping any control loop capability already offered by Magma.
      • Identify KPIs related to ONAP E2E Network Slicing that could become a requirement for Magma - Deadline: January 8th, 2021. Let's review any requirement on our first Enterprise call on 1/5/2022
  • Feedback from the "SABRES" working session organised on December 1st, 2021ONAP/Magma
    • SABRES Presentation from Gervais-Martial Ngueko
    • Next Steps:
      • Next meeting to be scheduled end of January 2022
      • Investigation about SABRES Resiliency and any other non functional requirements that might impact ONAP Integration
      • Send second iterations of the deck to Erik Kline including concrete questions
  • ONAP/Magma Integration Updates (Service Delivery)? Feedback about the onboarding of Magma VNF through SDC and next steps
    • Yogendra Pal has contacted the Magma team to perform helm chart changes
    • Is there any additional information to clarify the namespace usage?
  • LFN DDF event (Jan 10th-13th): Proposal has been submitted

Agenda - @7:30 am PST

  • Yogendra Pal ONAP/Magma Integration Latest Updates (Service Delivery)
  • Review any KPI Network Slicing requirement to be submitted to the Magma team 
  • Review our ONAP Enterprise Roadmap - what have we really completed in 2021 and what will be our 1H 2022 goals?  

Action Items (In Progress)

...