Info | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
|
...
- Some material:
Meeting Minutes - 3/3/2021
...
- Trudy Morgan : Present first ONAP/OPS-5G use cases
- 5 year effort - all work being done in the LF. Work will be up-stream w/o forking code
- NIWC: Naval Information Warfare Center
- Research project - all work is unclassified.
- Deck presented today: OPS 5G Use Case.pdf
...
#1 Create a dedicated controller via SDNC and handle Magma GW like any other device
#2 Have an adapter for the magma in ONAP Service Orchestrator and use it as a resource orchestrator for the specific jobs. Disadvantage: create something specific
#3 5G PNF Plug & Play and consider Magma GW as a PNF?
Current proposal: Avoid to create something specific but re-use what it is already developed in ONAP (SO/SDNC/SDNR) and orchestrate directly the Magma GW via gRPC
...
#4 Can we conclude Magma is an EMS (Element Management System)? YES
#5 5G Blueprint based on Guilin/Honolulu? Magma release is scheduled by June 2021 therefore let's consider ONAP Honolulu release
...
- Review of the integration with Magma Controller/GWs
- Code updated for AWS environments and is how available.
- Up and running with 2 deployments
- fully containerized GW planned for v1.6 ( ~4 weeks out)
- discussion this week and next should have sufficient content for the DTF
- standard SDC/SO/Multicloud model should be able to be used.
- potential for SDNC or CDS might be able to be used later - TBD
- Possibility of plug-n-play model to be used for AGW - something to look at
- Installing the access GW automatically would be valuable
- existing Magma baremetal upgrade model installs as a new package or collection of packages
- For ONAP assumption of initial deployments are PNF and time permitting then on CNF
- https://github.com/magma/magma/tree/master/experimental/cloudstrapper
- Suggestion to have a meeting next week at the same time with a smaller group. (TAC conflict noted)
- Same bi-weekly bridge to be used- David McBride will host, Kenny Paul will set up invite
- Information about Magma Security requirements @Arun Thulasi
- public certs are used for connects between internal components and HTTPS
- Magma provides the certificate to client
- https://docs.magmacore.org/docs/orc8r/architecture_modularity
- https://docs.magmacore.org/docs/orc8r/architecture_security
- https://docs.magmacore.org/docs/orc8r/architecture_overview
- The three above links should address some of the questions that we discussed in better detail
- DTF Event in June - 2021-06-DD - ONAP TSC Task Force: ONAP For Enterprise Business
- Is the slot OK i.e. Tue Jun 8 2021, 16:30 - 17:30 CET/10.30am-11.30am EST?
- Shall we meet on June 2nd, 2021 to finalize the DDF presentation?
- ONAP For Enterprise call will be canceled on June 9th due to DDF event.
...
2) If the underlying VIM provides APIs for placement of virtual resources on specific pieces of physical hardware, then does ONAP provide corresponding APIs that the VNFs can use to leverage these VIM placement APIs to perform precise placements of the virtual resources they use onto specific nodes within the physical infrastructure? It also depends on what the VNF/CNF/PNF provide as information. To be checked with our A&AI PTL - William
...