NameDescriptionVersion
DockerVM Container18 and above
ODL Yang ToolsYang model and Data Parser5.0.6 
Postgres Docker imageVM container for Postgres13.2-alpine
Open JDK imageBase image11-jre-slim
JettyApplication server9.4.31
SwaggerOpenAPI library2.1.4
SpringFoxOpenAPI library3.0.0
Hibernate typesSupport for Postgres datatype JSONB2.10.0
Spring BootApplication Framework2.5.0
cglib-nodep3pp3.1
commons-lang33pp3.11
antlr4-runtimeLanguage parser4.9.2
liquibaseDB Schema (version) management4.3.1

...


  • Testing and Integration Plans

Provide a description of the testing activities (unit test, functional test, automation,...) that will be performed by the team within the scope of this release.

Describe the plan to integrate and test the release deliverables within the overall ONAP system.
Confirm that resources have been allocated to perform such activities.

  • Gaps

This section is used to document a limitation on a functionality or platform support. We are currently aware of this limitation and it will be delivered in a future Release.
List identified release gaps (if any), and its impact.

...

  • Known Defects and Issues

Please refer to Frankfurt Defect Status

  • Risks

List the risks identified for this release along with the plan to prevent the risk to occur (mitigation) and the plan of action in the case the risk would materialized (contingency).

Please update any risk on the centralized wiki page - Frankfurt Risks

  • Resources

...


  • Gaps

No gaps Identified

  • Known Defects and Issues

See dynamic Jira filter:

Jira Legacy
serverSystem Jira
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
maximumIssues20
jqlQueryproject = CPS and type = bug and status = open
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176


  • Risks

No Risks identified, see also Istanbul Risks

  • Resources

Insert excerpt
Configuration Persistence Service Developer's Landing Page
Configuration Persistence Service Developer's Landing Page


  • Release Milestone

The milestones are defined at the Release Level and all the supporting project agreed to comply with these dates.

...

This section is optional and may be used to document internal milestones within a project team or multiple project teams. For instance, in the case the team has made agreement with other team to deliver some artifacts on a certain date that are not in the release milestone, it is erecommended recommended to provide these agreements and dates in this section.It is not expected to have a detailed project plan.

...

  • Documentation, Training

Please update the following centralized wiki: Frankfurt Documentation

...