Date | Event or Update | Milestones Affected |
---|---|---|
June 24 | Initial version of schedule approved by TSC by mail vote. | N/A |
July 9 | M1 milestone requirements not met. TSC agrees to slip M1 to July 13. | M1 |
July 13 | M1 milestone requirements not met. M1 slips to July 16. | M1 |
July 16 | Project milestone status 100%, but requirements still not resolved. M1 slips to July 23. | M1 |
July 23 | TSC approved M1 (2 week slip from original plan) | M1 |
August 6 | M2/3 milestone reqirements not met. M2/3 slips to August 11 | M2/3 |