Date | Event or Update | Milestones Affected |
---|---|---|
June 24 | Initial version of schedule approved by TSC by mail vote. | N/A |
July 9 | M1 milestone requirements not met. TSC agrees to slip M1 to July 13. | M1 |
July 13 | M1 milestone requirements not met. M1 slips to July 16. | M1 |
July 16 | Project milestone status 100%, but requirements still not resolved. M1 slips to July 23. | M1 |