MilestoneDescription DateComments
M2/M3Functionality Freeze / API Freeze


  • Final API definitions (swagger, Yang) due
July 3
  • Third party library version upgrades (per SECCOM recommendation) due
July 31, 2020Last day to submit Guilin swagger / Yang changes to Gerrit

  • M2/M3 Jiras ready for review
Aug 3, 2020Release manager reviews worksheets to assess readiness for M2/M3 milestone

  • M2/M3 Milestone
Aug 6, 2020


M4Code Freeze


  • Code due for Frankfurt user stories
Sept 4, 2020Last day to submit Frankfurt code changes to Gerrit

  • M4 worksheets ready for review
Sept 7, 2020

Release manager reviews worksheets to assess readiness for M4 milestone, including the following checks:

  • All repos must have >= 55% code (line) coverage in Sonar
  • No failed Jenkins jobs
  • All CSIT tests pass
  • Healthchecks pass

  • M4 release builds available
Sept 7, 2020

  • M4 Milestone
Sept 10, 2020


RC0Release Candidate 0


  • Code due for RC0 fixes
Sept 25, 2020Last date to submit code fixes for release candidate 0

  • RC0 release artifacts available
Sept 28, 2020

  • RC0 Jiras ready for review
Sept 28, 2020

  • TSC RC0 approval vote
Oct 1, 2020


RC1Release Candidate 1


  • Code due for RC1 fixes
Oct 9, 2020Last date to submit code fixes for Frankfurt release candidate 1

  • RC1 release artifacts available
Oct 12, 2020

  • RC1 Jiras ready for review
Oct 12, 2020

  • TSC RC1
Oct 15, 2020


RC2Release Candidate 2


  • Code due for final Frankfurt fixes
Oct 23, 2020Last date to submit code fixes for final Frankfurt release (RC2)

  • RC2 release artifacts available
Oct 26, 2020

  • RC2 Jiras ready for review
Oct 26, 2020

  • TSC RC2
Oct 29, 2020


Release Sign-OffFinal TSC Sign-OffMay 7, 2020
Frankfurt Release Sign-Off

...