Agenda Item

Notes

Action Items

Review Build Job Status

No issues


Review Recent CommitsNo changes since last meeting
Review Open Reviews

No reviews open


Review Current Sprint StatusAll tickets closed.
Guilin Release PlanningNo updates

Release Housekeeping


Per TSC decision, release has been pushed back.  See updated dates below.

Key Dates:

M4: Closed (3/3)

RC0: 3/26 → 4/16

RC1: 4/9 → 5/7

RC2: 4/23 → 5/21

Sign-off: 5/7 → 6/4


Any other topics

Committer elections complete. 2 new committers approved.  TSC responded on Junfeng committer promotion, but still waiting for approval on Alan Weinstock.  Once I have approval on both, we can move forward with INFO.yaml updates.  I need the email approvals to put in the INFO.yaml


Ticket: 

Jira Legacy
serverSystem Jira
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
keyVNFRQTS-884


Recordings and Other Attachments


No attendees at this session so no recording was made.  Please refer to the notes above.