The content of this template is expected to be fill out for M1 Release Planning Milestone.

...

Project Name

Enter the name of the project

Target Release NameGuilin
Project Lifecycle StateIncubation. Refer to ONAP Charter, section 3.3 Project Lifecycle for further information
Participating Company AT&T, ZTE

...

The scope of the Guilin Release of ESR will address Vulnerability Security Fix and Platform Maturity Requirements, as well the approved use cases.

Highest priority will be assigned to support security and platform maturity requirements.  As next highest priority, ESR will support the approved use cases.  Best-effort additional development will continue to support additional features not included in the approved use cases.

ESR R7 Guilin Release: Other requirements

Requirements


Minimum Viable Product

...

KeySummaryTCreatedUpdatedDueAssigneeReporterPStatusResolution
AAI-2888Upversion to DropWizard V2.0.2
Epic
Apr 29, 2020Apr 29, 2020
Peng HePeng He
Medium
开放未解决
AAI-2889Java 11 support
Epic
Apr 29, 2020Apr 29, 2020
Peng HePeng He
Medium
开放未解决
AAI-2890ESR Guilin Document
Epic
Apr 29, 2020Apr 29, 2020
Peng HePeng He

Medium

开放未解决
AAI-2891Kubernetes based Cloud regions Support
Epic
Apr 29, 2020Apr 29, 2020
Peng HePeng He
Medium
开放未解决




Stories



KeySummaryTCreatedUpdatedDueAssigneeReporterPStatusResolution
AAI-2847Added NFVO GUI internationalization file
故事
Mar 30, 2020Apr 29, 2020
Peng HePeng He

Medium

已关闭完成
AAI-2856Remove JQuery 1.11.0 from ESR Version
故事
Apr 07, 2020Apr 29, 2020
Peng HePeng He
Medium
已关闭完成
AAI-2857Upgrade to Apache Tomcat 9.0.31
故事
Apr 08, 2020Apr 29, 2020
Peng HePeng He

Medium

已关闭完成
AAI-2858Remove BootStrap 3.1.1 from ESR GUI
故事
Apr 08, 2020Apr 29, 2020
Peng HePeng He
Medium
已关闭完成
AAI-2859Upgrade to bootbox 5.4.0
故事
Apr 08, 2020Apr 29, 2020
Peng HePeng He
Medium
已关闭完成
AAI-2876Upversion to MSB-JAVA-JDK 1.2.5
故事
Apr 22, 2020Apr 29, 2020
Peng HePeng He
Medium
已关闭完成
AAI-2863Integrating aai-parent as the parent pom
故事
Apr 13, 2020Apr 29, 2020
Peng HePeng He
Medium
开放未解决
AAI-2892Change MSB Server Port in Test Case Code and Test it

故事

Apr 29, 2020Apr 29, 2020
Peng HePeng He
Medium
开放未解决
AAI-2895Resolve Esr-gui Root Running

故事

Apr 30, 2020Apr 30, 2020
Peng HePeng He

MediumImage Added

开放未解决
AAI-2896Resolve Esr-server Root Running

故事

Apr 30, 2020Apr 30, 2020
Peng HePeng He

MediumImage Added

开放未解决





Longer term roadmap

  • Focusing on security and reducing turn around on 3rd party dependency vulnerabilities
  • Enhanced UI of ESR GUI

...

Indicate where your project fit within the ONAP Architecture diagram.

Block and sequence diagrams showing relation within the project as well as relation with external components are expected.

...

List the API this project is expecting from other projects.
Prior to Release Planning review, Team Leads must agreed on the date by which the API will be fully defined. The API Delivery date must not be later than the release API Freeze date.

Prior to the delivery date, it is a good practice to organize an API review with the API consumers.

...

Name

Description

Version

BootStrapPopular framework for building responsive and a template starter page

4.3.1

JQuery

Open-source JavaScript Library

3.4.1
DockerVM container
DropWizardOpen-source Microservice application Java Framework1.3.0 or 2.0.2
Apache TomcatOpen-source implementation of the Java Servlet9.0.33
JerseyOpen-source  RESTful Web Services framework 2.16
JettyServlet Engine and Http Server9.4.22

...

Please update any risk on the centralized wiki page 

  • Resources

Fill out the Resources Committed to the Release centralized page.

  • Release Milestone

The milestones are defined at the Release Level and all the supporting project agreed to comply with these dates.

...

Each project must edit its project table available at Project FOSS.


Charter Compliance

The project team comply with the ONAP Charter.