Tasks/DeliverablesMost ProjectsVVPVNFREQINT
  • JIRA
    • All stories, epics, tasks, and subtasks (except documentation) should be closed
    • All high/highest priority tickets opened since RC0 should be closed
(tick)(tick)(tick)(tick)
Docker image release including bug fixes(tick)(tick)(error)(error)
Integration test status updated with % complete and estimated days to completion (integration test status page)(error)(error)(error)(tick)
CI Daily for Release(error)(error)(error)(tick)

RC2 (TBD)

Tasks/DeliverablesMost ProjectsVVPVNFREQINTDocumentation
  • JIRA
    • All stories, epics, tasks, and subtasks (except documentation) should be closed
    • All high/highest priority tickets opened since RC1 should be closed
(tick)(tick)(tick)(tick)(error)
  • Finalize documentation
    • Release notes, including security waivers
(tick)(tick)(tick)(tick)(error)All stories, epics, tasks, and subtasks (including documentation) should be closed
(tick)(tick)(tick)(tick)(error)
Final docker image(tick)(tick)(error)(error)(error)
Integration Release test status shows 100% completed and zero days remaining for testing(error)(error)(error)(tick)(error)
CI Daily for Release(error)(error)(error)(tick)(error)
  • Publish release documentation
    • Frankfurt branch for RTD
    • Update main page to Frankfurt, including version number
(error)(error)(error)(error)(tick)

Sign-off

  • Remaining high/highest priority jira tickets addressed or workaround documented
  • Close/move all open/in-process jiras to a future release
  • Integration "Sign-Off" on Docker images “Release” 
  • Release notes and documentation completed
  • OOM tag release and version in helm chart
  • Update the Frankfurt Release Key Updates