Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

  • API docs complete
  • Data Models (e.g, JSON, YANG, Swagger, etc.) shared with Modeling/Community
  • Architecture Review complete (if required)
  • No Gerrit requests older than 36 hrs.
  • Provide docker to integration testing for Wave1: oParent, PortalSDK
  • OOM port list update
  • Fix any Integration blocker - Daily status updates on integration blockers, Highest/High issues
  • Review and plan resolution of any License scan, security issues
  • Update Frankfurt Risks

M4

Note:  beginning with M4, we are customizing requirements for OOM, INT, VNFREQ, VNFSDK, and VVP.  M1 and M2/3 requirements will be customized beginning with Guilin.

Tasks/DeliverablesMost ProjectsVVPVNFREQ


New 3rd party dependencies, new FOSS (final confirmation)

(tick)(tick)(tick)


License scan issues addressed

(tick)(tick)(tick)


Address all security issues

(tick)(tick)(error)


All high/highest priority jira tickets addressed

(tick)(tick)(tick)


Update Frankfurt Release Platform Maturity, CII badging update - update M4 Result

(tick)(tick)(error)


Test coverage goals complete

(tick)(tick)(error)


No Gerrit requests older than 36 hrs.

(tick)(tick)(error)


Integration weather board update

(tick)

(error)

(error)


Update Frankfurt Risks

(tick)(error)(tick)


RCx

  • All high/highest priority jira tickets addressed
  • Remaining License scan, security critical issues addressed
  • Update Release note and documentation
  • Docker images “Release” dues 
  • Project specific test plan for El Alto completed
  • Update Frankfurt Risks
  • Integration Weather Board complete
  • Versioning at the project level
  • Check the certification expiry of your application. It should be valid for the next 9 months after RC0.

...