Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

  • Release, Security and Documentation scopes are now tracked via JIRA
  • Adoption to “Do not break the build” principle
  • No Vendor equipment is required for this release
  • No new VNF requirement identified by the project team
  • Jenkins Jobs Failures are monitored and fixed by the project team
  • Health check and regression tests issues are reported by the Integration Team
  • Project Team defines their Sprint content based on TSC prioritization to meet the delivery deadlines
  • Inform TSC about any descope content post-M1 before changing FixVersion

JIRA Template

Note that these Epics and Tasks are cloned into the JIRA project for each individual ONAP project.

Jira Legacy
serverSystem Jira
columnskey,summary,type,created,updated,due,priority,status,resolution,epic name
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
keyCIMAN-323

M1 

M1 

updated Oct 25

  • Define Frankfurt Scope with jira tickets labeled OR fixVersion
  • Any Architecture changes (Y/N)? Yes then require a ArchComm review plan
  • Any API changes Y/N
  • Any Data Model change Y/N
  • Any Impact on other components ( Y/N)
  • Frankfurt Release Platform Maturity v1 == Dublin goals - update M1 Target
  • New 3rd party dependencies, new FOSS? Y/N
  • CII badging update
  • Review code coverage goal vs. actuals
  • Change build process to adopt new oparent
  • Project specific test plan (automated unit test, sanity test/CSIT, pair-wise testing, etc) for full scope
  • 55% code coverage (set final goal after accessing jScript impacts) 
  • Fix Waiver granted by TSC from previous release
  • Fill in the  Release Planning Template
  • Assess Python3 migration status
  • Assess Java 11 migration status
  • Add project documents to document tracking table

M2/M3

  • API docs complete
  • Data Models (e.g, JSON, YANG, Swagger, etc.) shared with Modeling/Community
  • Architecture Review complete (if required)
  • No Gerrit requests older than 36 hrs.
  • Provide docker to integration testing for Wave1
  • OOM port list update
  • Fix any Integration blocker - Daily status updates on integration blockers, Highest/High issues
  • Review and plan resolution of any License scan, security issues
  • Begin release notes for Early Drop
  • Update Frankfurt Risks

...