  1. Navigate to 
    Jira Legacy
    showSummaryfalse
    serverSystem Jira
    serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
    keyREQ-1
  2. Select More==>Clone++
  3. Follow the steps in the dialog to clone the issue in the same project (i.e., REQ).  Make sure that the checkbox, "copy issues in epic" is selected.
  4. Modify the "epic name" and "description" fields for your requirement.
  5. Set the "Fix Version" field to the release name for which the use case is intended (e.g., "Frankfurt")
  6. Set the "Assignee" field to the requirement owner.
  7. If the requirement has other requirements or tasks as dependencies, add the requirements in the "Issues in Epic" field.
  8. Add a link to the JIRA issue in the appropriate column of the table on the release requirements page.
  9. Once the TSC has determined the priority for the requirement (0 - 4), set the value in the "TSC Priority" field.
  10. The template includes three sub-tasks for the TSC approvals at MS1, MS3, and MS4.  As these approvals are achieved, add a comment to the sub-task with a link to the approval documentation and mark the task as done.

Requirements Milestones Summary

Jira Charts
serverSystem Jira
jqlproject%20%3D%20REQ%20and%20issuetype%20%3D%20Task%20and%20%22Epic%20Link%22%20!%3D%20REQ-1
ystattypecustomfield_10001
chartTypetwodimensional
isAuthenticatedtrue
numberToShow999
xstattypeallFixfor
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176