The following items are expected to be completed for the project to Pass Release Sign-Off Milestone.
Release Sign-Off Milestone overview is available in wiki.
Usage
- Use the "Copy" and "Move" options (available under the ..., top right of this page) to duplicate this template into your project wiki.
- Fill out the Yes/No column
- Provide link to evidence (when necessary)
Practice Area | Checkpoint | Yes/No | Evidences | How to? |
---|---|---|---|---|
Product Management | Are committed Product Backlog Stories been coded and marked as "Closed" in Jira? | Yes |
Link to Jira
VFCAre all tasks associated with committed Product Backlog Stories been marked as "Closed" in Jira? | Yes |
Link to Jira
VFCProvide the project features list under the form of a bulleted list. | Link to evidence
2. |
Optimize the methodology for VNF(vdu) placement, add the process for placement with selected candidates(VIM)
3. Align VNFD SOL2.5.1 and model multi-version support
- Standard Alignment -SOL005 Alignment
- Maturity Enhancement
1.Mysql DB migrate to OOM shared MariaDB Galera Cluster
2. Configuration inject automatically
3. Add data persistent storage to avoid data loss due to pod restart
support CCVPN use case lifecycle management 3. support modeling parser for CCVPN use case 4. change database from mysql to postgreSQL | ||||
Summarize any functionalities that were planned at Release planning and not delivered at Release Sign-Off | No | |||
Release Management | Have all issues pertaining to FOSS been addressed? | Yes | ||
Have all findings from previous milestones been addressed? | Yes | Provide link to JIRA findings | ||
Development | Are all the Jenkins jobs successfully passed (verify + merge jobs)? | Yes | https://jenkins.onap.org/view/Merge-Jobs/ | |
Are all binaries available in Nexus Release repository? | Yes |
Provide link to evidence
https://nexus.onap.org/content/repositories/releases/org/onap/ |
Are all Docker images available In Nexus? | Yes |
Provide link to evidence
VF-CAre the Java and Docker manifest updated with the same version as in Nexus Release repository? | Yes | ||
OOM to Tag Release + Version in Helm Chart | Yes | ||
Integration and Testing | Have all CSIT Use Cases (created by each project team) passed? It should include at least 1 CSIT that will be run on Lab-xxx-OOM-Daily Jenkins Job | Yes |
Provide link to evidence
VF-C jenkins jobGoal is to incease our confidence the latest commit did not break the major functionality. Jenkins CSIT Jobs | |
Has the project code successfully passed the Daily Build process? | Yes |
Provide link to evidence
VF-C jenkins jobVF-CGoal is to ensure the latest project commit has not broken the Integration Daily Build | |||
Has the project passed the Integration Sanity Tests | Yes | Integration sanity tests in Dublin Release cover:
No test failure reported on http://onapci.org/grafana/d/8cGRqBOmz/daily-summary?orgId=1 No Integration Blocking Issue with no workaround: Dublin Release Integration Test Blocking Issues | |
Has the project done the integration testing with related dependent projects? | Yes | ||
Documentation | Has your team completed (reviewed, submitted and cherry picked) all documentation planned for the Dublin Release?
| Yes |
Provide Link to ReadTheDocs Release Notes
Provide Link to ReadTheDocs Project Documentation |
JIRA Query project != "Sandbox Project" AND project != "ONAP TSC" AND project != CI-Management AND (labels=Documentation OR project=Documentation) AND status != Closed ORDER BY fixVersion ASC, status DESC, priority DESC, updated DESC |