  • Identify/discuss gaps on current DCAE architecture for supporting edge requirement
  • Deeper dive in SDC artifacts created for MS and how models are utilized
  • VES agent work by Nokia/Team (requested by Alok)


 

Recording -  TBD

Action Items:

Vijay Kumar 

Complete and finalize documentation for Dublin - WIP (90%)

Create EPIC/JIRA and prioritize El-Alto - WIP (50%)

Vijay Kumar / Tony Hansen  - Follow-up with SECCOM team on xNF authentication/cert management process  (submitted - waiting for response from Amy)



 

...

...

  • Project Update - Vijay Kumar
    • RC0/1 status/update -ONAP_DCAE_05_16_2019.pptx
      • Current released docker version
    • El-ALTO DISCUSSION ITEMS- Tracker
    • Outstanding Branching/release/tagging for Dublin
      • dcaegen2 (documentation)
    • VES Spec - Update for batchEvent (limit to single domain/batch)

...

    • Project Administration - ONAP_DCAE_2019_04_11.pptx
      • Review previous action items
      • M4 Review
    • ONAP F2F Meeting update
      • Demo schedule for new components (SON-Handler/PM-Mapper/RESTConf/Heartbeat/BBS-Ep/VES-Mapper/Dashboard)
    • El-Alto Draft work-items - El-ALTO DISCUSSION ITEMS- Tracker
    • New VES Domain (trace3gpp) - Alok/Gerard
    • Need meeting will be hosted by Tony.

...

Vijay - El-Alto planning wiki for deferred items (DONE -  El-ALTO DISCUSSION ITEMS- Tracker)


 

    • Meeting cancelled due to ONS/ONAP F2F
       

...