R5 El Alto Release
EUAG recommendation is decided that R5 El Alto will be a "maintenance/technical debt" release.
https://wiki.lfnetworking.org/display/LN/EUAG+2019-04-09+meeting+minutes
The El Alto release could will be shortened and focus on internal (tech) debt and defect backlogs.
A proposed release cycle is presented.
PTLs had taken short cuts to meet deadlines, working but want to make the platform more robust. PTL driven code fixes and code hardening.
...
R5 - Security Scans, scan code reports sent to PTL for major things to fix. Vulnerabilities have been built. Vulnerability management process. Security gates checklist.
SUMMARY: what this means for the 5G U/C S/C ... in R5 there's no new content being introduced, no new Use Cases. Thus, nothing in any of our 5G U/Cs would be worked, but rather pushed to R6 FrankfurtNo new functionality will be introduced in R5 for the General PNF Support Use Cases.
R6 GENERAL PNF USE CASES OVERVIEW:
...