| Task | Start | End | Status |
---|
1 | Requirement Analysis |
|
|
|
1.1 | Finalize BBS architecture | Mon 11.26.18 | Tue 12.11.18 | Status |
---|
colour | Green |
---|
title | Completed |
---|
|
|
1.2 | Building Team | Mon 11.26.18 | Wed 12.05.18 | Status |
---|
colour | Green |
---|
title | Completed |
---|
|
|
1.3 | Create Epics In Community JIRA | Tue 12.11.18 | Fri 12.21.18 | Status |
---|
colour | Green |
---|
title | COMPLETED |
---|
|
|
1.4 | Create user stories In Community JIRA | Fri 12.21.18 | Tue 12.25.18 | Status |
---|
colour | YellowGreen |
---|
title | in progresscompleted |
---|
|
|
1.5 | Make Workloads, Acceptance criteria, Plan, Dependencies | Tue 12.25.18 | Mon 1.07.19 | Status |
---|
colour | Green |
---|
title | completed |
---|
|
|
1.6 | Low Level Design (Output specification for project design to review) 1. LLD for SDN-C & Access SDN M&C 2. LLD for SDN-C & Edge SDN M&C 3. LLD for VES Event definition 4. LLD for topology discovery from SDN M&C 5. LLD for External API 6. LLD for PRH enhancement
| Mon 1.07.19 | Mon 1.14.19 | Status |
---|
| |
---|
colour | YellowGreen |
---|
title | in progressCOMPLETED |
---|
|
|
1.7 | Low Level Design review | Mon 1.14.19 | Thu 1.17.19 | |
1.8 | Model freeze | Mon 11.26.18 | Tue 12.11.18 | Status |
---|
colour | Green |
---|
title | Completed |
---|
|
|
1.9 | Model review | Tue 12.11.18 | Tue 12.18.18 | Status |
---|
colour | Green |
---|
title | completed |
---|
|
|
1.10 | Model pushed to the community | Thu 1.24.19 | Tue 2.05.19 | |
1.11 | API freeze | Tue 12.18.18 | Tue 12.25.18 | Status |
---|
| |
---|
colour | YellowGreen |
---|
title | in progressCOMPLETED |
---|
|
|
1.12 | API review | Tue 12.18.18 | Tue 12.25.18 | |
1.13 | API pushed to he community | Thu 1.24.19 | Mon 3.04.19 | |
2 | Coding |
|
|
|
2.1 | Code Checkpoint 1 |
| Thu 3.07.19 |
|
2.2 | Code Checkpoint 2 |
| Thu 3.14.19 |
|
2.3 | Code freeze | Tue 12.25.18 | Mon 3.18.19 | |
2.4 | Weekly Code review | Tue 12.25.18 | Fri 2.08.19 | |
2.5 | Unit test | Tue 12.25.18 | Fri 2.08.19 | |
2.6 | Code pushed to the community | Tue 12.25.18 | Thu 3.28.19 | |
3 | Testing |
|
|
|
3.1 | E2E Test design and demo strategy | Mon 1.07.19 | Wed 1.16.19 | Status |
---|
| |
---|
colour | Yellow |
---|
title | in progress |
---|
|
|
3.2 | E2E Test design and demo strategy review | Wed 1.16.19 | Fri 1.18.19 | |
3.3 | Internal Demo review | Mon 1.07.19 | Tue 3.12.19 | |
3.4 | Develop test plan | Fri 2.08.19 | Tue 2.12.19 | Status |
---|
colour | Yellow |
---|
title | in progress |
---|
|
|
3.5 | Project Test case output | Fri 2.08.19 | Tue 2.12.19 | |
3.6 | Project Interface self test | Fri 2.08.19 | Wed 2.27.19 | |
3.7 | Integration test plan | Fri 1.18.19 | Fri 1.25.19 | Status |
---|
colour | Yellow |
---|
title | in progress |
---|
|
|
3.8 | Integration Test case output | Fri 1.25.19 | Sat 1.26.19 | |
3.9 | Integration test | Fri 2.08.19 | Sat 3.09.19 | |
3.10 | Internal Demo Show Round1 | Mon 3.11.19 | Thu 3.14.19 | |
3.11 | Internal Demo Show Round2 | Mon 3.18.19 | Thu 3.21.19 | |
4 | Lab Setup |
|
| Status |
---|
| |
---|
colour | Green |
---|
title | completed |
---|
|
|
4.1 | Development Environment (CI/CD, Code repo) | Mon 11.26.18 | Fri 12.07.18 | Status |
---|
colour | Green |
---|
title | completed |
---|
|
|
4.2 | Development Environment (local env, local test env) | Mon 11.26.18 | Fri 12.07.18 | Status |
---|
| |
---|
colour | Green |
---|
title | completed |
---|
|
|
4.3 | Detailed lab topology (wiring diagram) | Wed 12.26.18 | Wed 1.09.19 | Status |
---|
colour | Green |
---|
title | Completed |
---|
|
|
4.4 | Detailed lab topology (wiring diagram) review | Wed 1.09.19 | Wed 1.09.19 | Status |
---|
colour | Green |
---|
title | completed |
---|
|
|
4.5 | Material ready | Wed 12.26.18 | Wed 1.09.19 | Status |
---|
colour | Green |
---|
title | completed |
---|
|
|
4.6 | Demo Lab setup | Fri 2.01.19 | Mon 2.25.19 | Status |
---|
colour | Green |
---|
title | completed |
---|
|
|