- Status and Stucks
Current POMBA Dublin Stories (Logging Project) -
Current Code Inspections
- POMBA 6 hour healthcheck (full 200G CD deployment) - http://kibana.onap.info:5601/app/kibana#/dashboard/AWAtvpS63NTXK5mX2kuS
General Status
- Dublin
- Stories in progress:
Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-959 Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-551 Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-665
- Stories to be formally verified before closure:
Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-779 Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-957 Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-404
- Stories closed since last meeting:
Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-766 Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-767 Jira Legacy server System Jira columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-778
For network resource only and should be split into Network Discovery and ND context builder.Jira Legacy server System Jira columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key SDNC-475 Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key SDNC-637 Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-958
- Bugs to enter:
- Latest security scan results show ~9 medium issues that should be recorded (but aren't severe enough to merit immediate work).
- Bugs entered in last week:
Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-1014 Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-1013
- Bugs in progress:
Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-712 Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-658 Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-987
- Bugs to be verified:
(Verify in OOM fails, assigned back to design)Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-803 Jira Legacy server System Jira columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-808 Jira Legacy server System Jira columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-1001 Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-988 Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-975 Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-976
- Bugs closed off since last meeting:
Jira Legacy server System Jira columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-999 Jira Legacy server System Jira columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-998 Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-996 Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-996 Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-839
- Stories in progress:
- Dublin
- Technical Discussion
- Consider demo schedules
- J. Ram Balasubramanian will forecast demos as development progresses
Data Dictionary & Network Discovery- Dec 20Done
L2 Network data (Feb 21)- video available
- Additional enhancement - March 21st
- additional resources and rules
- potentially other enhancements
- Or We shall do Tuesday at 11 in logging meeting to get more people?
- send email to advertise
- Sharon to follow up with Michael O. Note Logging meeting only happens every two weeks, although the zoom is available.
- Logging Timeslot (11am eastern), Tuesday March 26th
- J. Ram Balasubramanian will forecast demos as development progresses
- Note we have discovered a number of discrepancies between the model definition in the wiki and the code. We are now raising bugs on specific issues found and will resolve as appropriate.
- Bugs raised; Issues fixed. Found a few more issues yesterday, which are being worked.
- Chesla to review mapping and provide feedback
- common model: https://wiki.onap.org/display/DW/POMBA+Common+Model
- This is out of date.has been updated
- common model mapping: https://wiki.onap.org/display/DW/Dublin+Common+Model+Mapping
- Reflects what has been implemented after some updates
- common model: https://wiki.onap.org/display/DW/POMBA+Common+Model
- Not all containers have health check enabled
The gaps should be tracked. Action J.Ram.Updated. Only 3 microservices currently have healthcheck on them. Updated onJira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-432
- Validation Service and adding rules
- Action Yong to improve page or create a new one with better steps.
- Work has been done and Brian has seen
- Still looking for feedback from various folks and will update as appropriate.
- Status: Closed
- Consider demo schedules
- There might be a late change to the PNF model
- We might get impacted
- Will they be backwards compatible? Ie, versioned
- Sharon to follow up Jimmy.
The plan of record in Dublin has the key of the PNF object changing from pnf-name to pnf-id. This means a migration in systems that use the PNF object.
There are still discussions underway to reduce impact to clients, and we don’t have the official path forward on how this works (and there are also discussions about NOT introducing a breaking change in the API). I think we’ll have a path forward next week, I’ll loop you in when I know which direction it’s going.
- This would impact POMBA if we do get by id, this will impact us. If we are using a query string, we would be fine.
- Action J.Ram to confirm which we use.
- Making the PTL Happy
- Casablanca
- Release notes being prepared.
- Still seems to be open.
Data router version was upped. So, POMBA needed to update its version. This was integrated.There was a bug and the A&AI team fixed it. Integration team tested the fix, but perhaps did not test POMBA
J. Ram will quickly test.Michael O. did test already that the POD comes up and passes health check.J. Ram will confirm we did an audit.- Updated on
Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key AAI-2090 - Closed
Dublin- Updated on
- From PTL
- If you have concerns bring them to the TSC or the PTL meet - as I have a hard time convincing the TSC about issues without more developer voices
- Also for committer promotion - the template needs more data - 90/180/360 day commits, jira, discuss groups, wiki, reviewed commits, meeting attendance - as one of the committers for integration was rejected last week - any developer listed for committer promotion must attend the TSC 9-1030 to promote themselves and answer questions
- details of what people have contributed, Jira, etc
- Action Sharon: Send information. .
- Action Yong : follow up to get information
- (+) 20190228: manifest confusion being addressed in TSC 2019-02-28 for
Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-966 - This is related to integration testing using predictable environments
- No resolution yet, but it is being discussed.
- Should look at milestones and ensure we are in good shape.
- API freeze is March 14th (or has this slipped?)
- Michael is starting to put together M3 checklist.
- POMBA is ok for M3, according to Michael O.
- API freeze is March 14th (or has this slipped?)