Unit, Functional testing, Pair-wise testing. Where should we document the test cases prior to submission and passing on to integration. 3rd party/vendor domain external controllers.
API IMPACTS SUMMARY
The following table summarizes the expected API impacts for each of the 5G Use Cases.
These are needed for the M3 R4 Milestone (Mar 14)
USE CASE | API Impacts |
---|---|
Bulk PM | DMaaP DR API Updates. Next Steps: Confirming API details. |
Configuration with NetConf | Separate initiative E2E automation via CDS. Added new API between SO & Controller Design Studio (CDS). CDS team is defining this new API. This U/C will use that new API. Next Steps: Dependency between this U/C with the CDS work. Basic support of API has been delivered. Some API details to be finalized. |
OOF / PCI | API changes are needed. Config DB, SDN-R. APIs for individual nodes record updates in Config DB. Bulk APIs for updating. API associated with SDN-C project. SON MS & Policy & OOF Next Steps: JSON swagger document being produced. |
PNF Plug and Play | New API for the Update Micro-service to SO (from the pnfUpdate event trigger) from Policy for the Reregistration Story. The "user" will be the BBS Micro-service U/C. Next Steps: Ajay in DCAE has accepted this micro-service. Final details of the new service-update API is being defined in conjunction with SO project (Seshu). |
PNF S/W Upgrade | Roll-back API. From SO to SDN-C (Controller). South-bound changes (captured in the Ansible Playbooks), impacting the external controller rather than the ONAP platform. Data pushed from API so s-bound APIs will have right data (in the payload). Next Steps: Plan for next week (Mar 6), will have draft for API. |
USE CASES WITH NO API IMPACT | |
PNF Pre-onboarding / Onboarding | No API Impacts. |
5G FM Meta Data 5G PM Dictionary | No API changes |
Network Slicing | (Modeling only) - No API Changes |
USE CASE REALIZATION MEETINGS
...