Practice AreaCheckpointYes/NoEvidence - CommentHow to?
SecurityHas the Release Security/Vulnerability table been filled out in the protected Security Vulnerabilities wiki space?Yes

Table in the protected Security Vulnerabilities wiki space corresponds to the latest NexusIQ scan

R4 CLI Security/Vulnerability - Full Content


Have known vulnerabilities (critical and severe) to address/remove in the release been identified with JIRA ticket?Yes

No vulnerabilities planned to address as they does not affect as reported in vulnerabilities table

Create JIRA tickets
Has the project committed to the release CII badging level?NoNo plan

See https://www.coreinfrastructure.org/programs/badge-program/

or CII Badging Program

Has the project created their project CII questionnaire and completed the ONAP level CII requirementsYes
See CII Badging Program
If the project uses java, has the project integrated with the oparent.pom?YesOparent.pom included in the project
Product ManagementAre Product Backlog Epics entered in Jira?YES

Jira Legacy
serverSystem Jira
jqlQueryproject=cli and fixversion="Dublin Release"
counttrue
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176

Create a Backlog item

Difference between a Product and Sprint Backlog

Are Product Backlog Stories entered in Jira?YES

Jira Legacy
serverSystem Jira
jqlQueryproject=cli and fixversion="Dublin Release"
counttrue
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176

Create a Backlog item
Are Product Backlog Stories linked to Product Backlog Epics?YESProduct BacklogWork in a Sprint
Are Product Backlog Stories prioritized?YESProduct BacklogPrioritize a Backlog item
Is the project team ready to estimate the top Stories (for coming Sprint) in Product backlog?YES

Jira Legacy
serverSystem Jira
jqlQueryproject=cli and fixversion="Dublin Release"
counttrue
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176

Estimate a Backlog item
Is the project team ready to create a 2 weeks Sprint in Jira?YESSprint 1 in progressCreate a Sprint
Are Team Members willing to create Tasks and associate them with Stories in Jira?YESSprint 1in progressCreate a Backlog item
Release ManagementIs there a Release Planning Template available and completed in wiki?YESDublin-M1-CLI Release planning
Have all the "Release Components Name" been defined in Resources and Repositories (Deprecated) for your project? (this includes all Sub-Components Names, Sub-Components Repositories Names, Maven Group ID, Sub-Components Description)YESResources and Repositories (Deprecated)
Have all the "Resources committed to the Release" been defined in Resources and Repositories for your project? This includes First and Last names, LFID, Email Address and Location for PTL, Project Manager, Committers and Contributors.YESResources and Repositories (Deprecated)
Have new developers made themself familiar on the Onboarding Process?YES
Onboarding
Is the project team aware of the Release milestone? Any misses will required TSC exception.YES

Integration and TestingHas the Integration Team defined the vendor equipment list?NALink to evidence
Has the Integration Team defined the End 2 End Release Test Case?NOLink to evidence




Development



Is the Project Team committed to develop Unit Test?

YES

Has the Project Team put in place an Automated Unit Test infrastructure?YES

Is the Project Team committed to create Continuous System Integration Testing (CSIT) test case?YES

Is the Project Team committed to perform Scrum ceremonies?YES
Scrum Overview
Are the Project Team members aware of Continuous Integration Principles (don't break the build, Fix the build,...)?YES
Continuous Integration
Has the Project Team a clear understanding on the Code Coverage expectations?YESUnderstood it as >50 %

Code Coverage and Static Code Analysis

Does the Project Team understand the Free and Open Source Software (FOSS) process?YESCLI FOSSFree and Open Source Software
Is the Project Team willing to fill out accordingly the FOSS table?YES
Fill out sub-pages for each project under Free and Open Source Software
Is the Project Team willing to comply to the Commit Process?YES
Commit Messages
Does the Project Team understand the purpose of Code Review?YES
Code Review
Is the Project Team aware of the Coding Guidelines?YES
Development Practices (Jave Coding Style)





...