Project Name | Portal Platform |
---|---|
Target Release Name | R4 Dublin Release |
Project Lifecycle State | Incubation. Refer to ONAP Charter, section 3.3 Project Lifecycle for further information |
Participating Company | AT&T, ChinaMobile, IBM, Amdocs |
Scope
What is this release trying to address?
Scope: The scope of this release will be for the Portal Platform to support the below list: (provided the lead developers names who will be providing status on these committed features in weekly scrums)
5G Usecase Impacts on Portal platform (AT&T resources - Former user (Deleted) )
...
- Locale/Internationalization language support – UsecaseUI project integration. (Chinamobile resources committed for this feature - Tao Shen)
- Reporting feature enhancement in portal/sdk (AT&T resources - Former user (Deleted) )
- Angular 6 Upgrade of ONAP Portal and SDK with 1 or 2 new UI screens (IBM and AT&T resources partially committed - Deven and Saravanan Madheswaran)
- may impact partnering apps like Policy and VID
House Keeping (AT&T resources - Lorraine A. Welch, Amdocs resources)
- Maintain documentation for the architecture, APIs and release notes. (AT&T resources - Lorraine A. Welch)
- Improved logging - (Amdocs resource - Michael O'Brien )
Test Automation (IBM resources partially committed - Sireesh Chintamani (Deactivated) )
...
Indicate at a high level the longer term roadmap. This is to put things into the big perspective.
Draft requirements Requirements for next Dublin release - road map
Release Deliverables
Indicate the outcome (Executable, Source Code, Library, API description, Tool, Documentation, Release Note...) of this release.
...
Sub-components are repositories are consolidate in a single centralized place. Edit the Release Components name for your project in the centralized page.
...
List the API this release is expecting from other releases.
Prior to Release Planning review, Team Leads must agreed on the date by which the API will be fully defined. The API Delivery date must not be later than the release API Freeze date.
Prior to the delivery date, it is a good practice to organize an API review with the API consumers.
...
Gaps identified | Impact |
---|---|
Security (No committed resources)
New features (No committed resources)
Address ONAP Platform Maturity Guidelines (No committed resources)
House Keeping (No committed resources)
| Updated in Dublin Risks Risk#3 - Security impact on Policy, VID apps that use portal/sdk regarding addressing NexusIQ security issues and AAF integration which is not committed by Portal team so far due to lack of resources; Risk#4 - Impacts Dublin platform maturity requirements (Footprint Optimization, Logging Capabilities). Also, OOM deployment is impacted if the DB scaling changes are not supported by Portal team; also the changes for simplification of etc/hosts entries impacts the OOM deployment which is not committed by Portal team so far due to lack of resources. |
...
Risk identified | Mitigation Plan | Contingency Plan |
---|---|---|
Resources | Actively seeking community support. | Current resources are not enough to satisfy even the Highest Priority Epics |
Resources
Fill out the Resources Committed to the Release centralized page.
Release Milestone
...
The project team comply with the ONAP Charter.
Release Key Facts
Fill out and provide a link toward the centralized Release Artifacts.