- TSC agrees to cancel the TSC Call on November 1st, 2018
- TSC agreed to proceed without "5G PNF Live Mngt Support" excluding steps 36/37 (TSC-26)
- TSC approved the ONAP Release Manager RC1 recommendations i.e. Grant RC1 to16 out of 30 projects.Conditional on all other Projects in addressing Orange and Red Items by Oct 31st, 2018
https://wiki.onap.org/download/attachments/45296866/ONAP%20Casablanca%20RC1%20Status%20Summary%20Oct25Version1.pdf?version=1&modificationDate=1540553903000&api=v2
November
11/08
- TSC agrees to cancel the TSC Call on November 22nd, 2018
- TSC agrees to shift the Casablanca RC2 (Nov 8th → Nov 27th); Casablanca Sign-off (Nov 15th → 30th); Plan an extra-Ordinary Casablanca Release Maintenance on Jan 31st, 2019 including any use case not passing RC2 milestone criteria
...
- TSC agrees to cancel the TSC Call on December 27th, 2018
12/11
- TSC votes on 2019 Budget Reductions Action
...