TestCase IDTestCase NameProgressNote?(Issue Record?)

 Lab infrastructure preparation: including hardware, VIMs, sotn controller, SD-WAN controller, PNFs / VNFs installation  

100%
T00001

 Install ONAP and health check 

100%
T00002SOTN Controllers  Registration100%
T00003SD-WAN Controllers Registration100%
T00004

CCVPN Resource Template Import  

100%
T00005

SOTN VPN Infra Service Design 

60%
T00006

Stie Enterprise Service Design 

60%
T00007

Site DC service Design 



T00008

SDWAN VPN Infra service Design



T00009WAN Connection service Design

T00010

 SOTN Network Topology Discovery 

100%
T00011

 SOTN Link Management  



T00012CCVPN E2E Service Creation

T00013CCVPN  E2E Service Termination

T00014Close-Loop Recovery 

...

Test NO:

TEST-09

Project:

Closed Loop

Sub-project:

Closed Loop in ONAP SOTN link

Objective:

ONAP can find SOTN network cross domain link interruption automatically, and rebuild SOTN business automatically.

Pre-condition:

  1. All elements of OTN network TOPO environment has been completed.
  2. CCVPN services have been created and bussiness is working fine.

Test step:

  1. Interrupt the cross domain link in the CMCC side ONAP manually.


Test Result:

  1. Closed-loop triggered automatically, SOTN link will be recreated through another cross domain link.


Observation:

  1. Check all the CCVPN services are work fine as in “CCVPN Service Instantiation”

...