...
- Status and Stucks
Current POMBA Casablanca Stories (Logging Project) -
Current Code Inspections
- POMBA hourly healthcheck (CD deployment) - http://kibana.onap.info:5601/app/kibana#/dashboard/AWAtvpS63NTXK5mX2kuS
- General Status
- Casablanca
- Done, as per last week.POMBA-associated OOM bug still to be merged
Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key OOM-1465
- Done, as per last week.POMBA-associated OOM bug still to be merged
- Dublin
- SDNC Context Builder w/ Generic Resource API testing completed [LOG-520, LOG-462]
|Jira Legacy server System Jira columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-520 Jira Legacy server System Jira columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-462 - Still waiting on OOM branch for SDNC Context Builder deployment. (~November/December) [
]Jira Legacy server System Jira columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-426 - We will opt to wait it out rather than submit to Casablanca and disable
- Additional OOM-reliant work (e.g. validation rules) should be (and is being) deferred in schedule
- SDNC Context Builder API Mapping + VNF API completed and merged submitted (to Dublin branch); merge and minor paperwork items to clean up [up
]Jira Legacy server System Jira columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-421 - Updated Common Model groundwork completed; implementation begun [
]Jira Legacy server System Jira columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-780
- SDNC Context Builder w/ Generic Resource API testing completed [LOG-520, LOG-462]
- Casablanca
- Engage Integration Team now?
- Sharon sent email to Brian and Helen.
- Could have replied to Robot email chain as well.
- In addition, we ourselves can run POMBA audits based on data in integration lab, in our own instances.
- Chesla and others will try this.
- Technical Discussion
- POMBA Common Model update [Geora]
- Wiki: POMBA Common Model
- Story:
Jira Legacy server System Jira columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-780
- ONAP Common Model update? [Chesla]
- TOSCA task force. How to use end to end through lifecycle through project
- May impact what sort of rules we can source from the model
- Will take time.
- Two internal data model
- VFC
- SO, SDNC, etc
- Trying to bring it together.
- TOSCA task force. How to use end to end through lifecycle through project
- POMBA Common Model update [Geora]
- Making the PTL Happy
- ONAP Casablanca RC0 Milestone achieved(?)
- Logging project checklist: Logging Casablanca RC0 Deliverables for RC0 Milestone Checklist Template
- POMBA okay:
- build jobs passing
- CLM issues resolved
- pair-wise chart populated
- Integration Weather Board: Integration Weather Board for Casablanca Release
- ONAP Casablanca RC1 Milestone – today?
- Logging project checklist: Logging Casablanca RC1 Deliverables for RC1 Milestone Checklist Template
- What do we need to do, if anything in POMBA?
- ONAP Casablanca RC0 Milestone achieved(?)