- Status and Stucks
Current POMBA Casablanca Stories (Logging Project) -
Current Code Inspections
- POMBA hourly healthcheck (CD deployment) - http://kibana.onap.info:5601/app/kibana#/dashboard/AWAtvpS63NTXK5mX2kuS
- General Status
- Casablanca
- Wiki updates completed
- Resource limits/chart issue has been fixed.
- Pairwise testing table has been updated
- So, we are basically done.
- Dublin
- SDNC Context Builder w/ Generic API merged
- OOM branch not available until ~November
- Jobs enabled
- SDNC Context Builder w/ selection + VNF API mostly complete (working on VNF API and need to do designer testing)
- This is the 'mapper' plus able to support VNF API
- SDNC Context builder has Dublin branch, others don't
- OOM, etc won't have branches until November. Means we can't close stories.
- Might be able to submit and have disabled in OOM. That would be in the Casablanca branch.
- Everything non-OOM, we should be able to cut branches earlier as we have control.
- OK, for everything but new microservices and rule updates.
- Started offline discussion on model updates to support Dublin content. Will review with team shortly.
- SDNC Context Builder w/ Generic API merged
- Casablanca
- Engage Integration Team now?
- Sharon sent email to Brian and Helen.
- Could have replied to Robot email chain as well.
- In addition, we ourselves can run POMBA audits based on data in integration lab, in our own instances.
- Chesla and others will try this.
- Sharon availability (start a 'working holiday' Oct 24-Nov 7). Someone may need to cover to cover this meeting. David or Michael.
- Technical Discussion
- SDNC Mapping
- Making the PTL Happy
- RC0 is the next milestone. Oct 18.
- All builds must pass
- All CLM high issues resolve
- POMBA ok
- Pair-wise testing. Fill in page.
- Prudence and Michael have worked.
- Integration weather board filled in
- Should be ok. Mostly green.
- RC0 is the next milestone. Oct 18.