Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Practice AreaCheckpointYes/NoEvidencesHow to?
Product ManagementAre all tasks associated with the release been marked as "Done" in Jira?In-progress

Done.

Jira Legacy
serverSystem Jira
jqlQueryproject=dcaegen2 and type in (Story,Task) and fixversion="Casablanca Release" and status in (Closed,Delivered,Done)
counttrue
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
 


Not completed

Jira Legacy
serverSystem Jira
jqlQueryproject=dcaegen2 and type in (Story,Task) and fixversion="Casablanca Release" and status not in (Closed,Delivered,Done)
counttrue
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
 






Have all findings from previous milestones been addressed?Yes

CSIT issues addressed

Daily Jenkins jobs for tca-gen2 addressed


DevelopmentHave all Defects of priority Highest and High been in status "Done" in Jira?Yes

Jira Legacy
serverSystem Jira
jqlQueryproject=dcaegen2 and type = story and fixversion="Casablanca Release" and priority in (High, Highest) and status not in (Closed,Delivered,Done)
counttrue
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176


Are all JIRA issues used as a reference in a commit in status "Done" in Jira?Yes
Very often, some JIRA issue remains in status "Todo" in JIRA while the commit they are referenced to is successful.
Is there any pending commit related to Highest and High priority issues older than 36 hours in Gerrit? In case there are messages going back and forth between authors and reviewers, it is acceptable to be above 36 hours.No

Are all the Jenkins jobs successfully passed (verify + merge jobs)?Yes

Has the team delivered all their release artifacts in Nexus Release or Nexus Staging repo?

There should be at least ONE version of each artifacts available in Nexus Release or Nexus Staging repo.

In-progress

All components released except PRH

Refer to Independent Versioning and Release Process for procedure
Integration and TestingHave all CSIT Use Cases (created by each project team) passed?No1 job failing (dcaegen2-master-csit-prh-testsuites) being worked
At RC0, has the Pair Wise testing table been filled out?YesDCAE Pair Wise Testing for Casanblanca Release
At RC0, have all OOM Release Healtcheck related to your project passed?Yes  
At RC0, is there a Docker image in Nexus Docker-Release repo available for each repository?In-progressOne repo - PRH remaining pending CSIT resolution 
Has the project code successfully passed the Daily Build process?Yes
Goal is to ensure the latest project commit has not broken the Integration Daily Build 
Has the OOM deployment passed?YesInterface testing with SDC/CLAMP/Policy pending
Has the Heat deployment passed?Yes

Documentation

For RC0, for project delivering binaries, has the team populated and validated all the sections of either the Platform Component or SDK template?


NoIn-progress

Most teams have already created the high level file structures in readthedocs, and populated some actual documentation. However, the remaining sections of the appropriate teamplate must be completed.

Platform: A&AI, APP-C, CLAMP, CLI, DCAE, DMaaP, Holmes, MSB, OOM, Policy, Portal, SDN-C SDC, SO, UseCase UI, VFC, VID

SDKs: AAF, CCSDK, External API Framework, Multi VIM/Cloud, VNFSDK

For RC1, has the team addressed any issue (recorded in JIRA) provided by the Documentation team?

NA

For RC2, for project delivering binaries, has the team populated and validated all the sections of the Release Notestemplate?

NA

For RC2, has the Documentation Team provided the final approval for your project documentation?NA

...