  1. M3 Due  8/23/18 finalize :
    1. Portal-343 Sireesh will check in today or tomorrow - done
    2. Portal-247 Sonar scan Hari - Leimeng send him an email in-progress
    3. Portal-272 Sireesh will change status - adding more test cases:for Language, SDK, etc
    4. Portal-316 and  Portal-314 turn on Raptor Reports on VM 11 menu for SDK - Leimeng,; menu in gerrit has to be activated if it passes; Portal-314 is closed
    5. Portal-275 check to see if postponed to Dublin - Lorraine check today
    6. Portal- 288 code is done, documentation needs to be updated and code to be tested - Sunder ??
    7. Portal-362 Lorraine submitted, Sunder to merge - done
  2. Code Coverage needs to be maintained at 50% or the current coverage better than 50%. (70% on Portal, on  64% SDK) - check offline
    1. SDK repo - Naveen is working on new SDK code coverage changes. New SDK commits made - Please add more reviewers - "Amrita Kundu" <amrkundu@in.ibm.com> and Mani are working part time on the code coverage 
    2. Prasad/Swapnali - not active on the code commits. 
    3. Please use Epic - PORTAL-268 - for code coverage - PORTAL-273; for sonar issues - PORTAL-247; (focused on Portal repo).
  3. Design for Angular update 
    1. Source code to be committed for Angular upgrade in a separate folder under SDK (waiting on fixing the build process which is taking long) - gerrit review is done - waiting to merge.
      1. update the xml file - Saravanan.- still reviewing, pending
    2. Bump up the pom and docker versions to snapshots and deploy to T-Lab and Windriver (change in OOM as needed) - Saravanan/Sunder/Manoop.
    3. fonts and icons abstraction so that they can be switched with a flag configuration - Saravanan (decided to achieve this configuration during the build rather than at runtime)
    4. One screen implementation needs review with Sunder. - complete , will meet before checking the code
  4. Lorraine to run grep scan for ecomp keyword  - done - Review with Sunder/Manoop - will send them result in email - forward scan email to Hima and Lorraine
    1. Look for the vm host names in the files - to clean up - Lorraine already made commit for this changes - Hima can help if requires java file changes.
    2. ECOMP to ONAP word changes in license text - done in Code Cloud - waiting to move to Gerrit - 08/01
    3. Need to review the MUSIC related classes to cleanup the ECOMP keywords - Hima looking into it. (changes are being committed in internal codecloud, soon will be pushed to gerrit).
    4. Hima working through changes - still working on it , Lorraine will help
  5. Moving the current CSIT tests to test-suites repo - may need to create a new JIRA item to track - Sireesh/Ritesh - 
    Jira Legacy
    serverSystem Jira
    serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
    keyPORTAL-343
    1. Submit the changes into test-suites and add reviewers - Brian Freeman and Gary Wu - ETA 08/13 - done
    2. Reviews being done and Sireesh fixing the files. - done
    3. Once merged, please request Gary to trigger portal scripts from External labs OOM jenkins jobs - Sireesh. - working with Gary
    4. Runs from local, needs to be tested in Jenkins
  6. Sireesh/Ritesh to plan the test cases for the new features planned to Casablanca - Portal R3 Casablanca Functional Test Cases
    1. Regarding reporting feature - there is meeting scheduled for Friday. - meeting was held, some test cases are written
    2. Regarding language feature - following up with Tao Shen. - had a call, Tao sent document  (5 APIs), GUI page needs updating Leimeng will sent email, another meeting Friday
  7. Sireesh/Saravanan to followup with Sitharam for resources on AAF - CADI risk in Portal - Looking for response from Sitharam - meeting happened on 8/14
    1. Two resources expected from ECOMP's team (Sireesha and Hima/Hema).
    2. SITHARAMAN T R to provide list of resources for this task.
    3. Sunder Tattavarada and Manoop Talasila to prepare the plan and tasks for this feature and provide ETAs.
    4. Jonathan Gathman from AAF to provide support and guidance on all the AAF details. Had call with Jonathan, Sunder working on it, Saravanan - certificate work will be done after Sunder gives them info
    5. met with Jonathan 70% done; 
    6. two steps 2.4 has rest implementation done; 2.5 will have CADI; email sent and partners 
    7. Jonathan having a few roadblocks, has to make some changes
  8. Logging standards analysis done by Lorraine - link to the expected changes for logging -  ONAP Application Logging Specification v1.2 (Casablanca)
    1. Micheal O Brien reviewing the logging changes that can be done in portal/sdk - followup - 
      Jira Legacy
      serverSystem Jira
      serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
      keyPORTAL-170
      .
    2. Review the current MDCs in the "EPEELFLoggerAdvice.java" class and others that might have.
    3. Lorraine will follow up with Michael tomorrow .
    4. Review needs to be done with Sunder, Shireesha. Kotta by Sep 1st week with Michael's changes
    5. Some of the logging code is being refactored

Attendees:  and Hima

Image RemovedImage Added

Release Discussion Items:

...

Casablanca Release (Nov 2018)

...