The following items are expected to be completed for the project to Pass the M3 API Freeze Milestone.
M3 Release Architecture Milestone overview is available in wiki.
Info | ||
---|---|---|
| ||
|
Practice Area | Checkpoint | Yes/No | Evidences | How to? |
---|---|---|---|---|
Architecture | Has the Project team reviewed the APIs with the Architecture Committee (ARC)? | Yes | yes review done on the 14/8 | |
Is there a plan to address the findings the API review? | yes | no findings | ||
Does the team clearly understand that no changes in the API definitionisallowed without formal TSC review and approval? | Yes | |||
Is there any changes in the scope, functionalities, deliverable, dependency, resources, API, repositories since M1 milestone? | No | |||
Providelinkto the API Documentation. | SDC API | |||
Release Management | Are committed Sprint Backlog Stories been marked as "Done" in Jira board? | Yes | ||
Are all tasks associated with Sprint Backlog Stories been marked as "Done" in Jira? | Yes | |||
Have all findings from previous milestones been addressed? | Yes | |||
Development | Has the project team reach the Automated Unit Test Code Coverage expectation? (Refer to artifactsavailable in Sonar) | No | Goal: 30-50% for Incubation project | work in progress |
Is there any pending commit request older than 36 Business hours in Gerrit? | YesIn progress | a number of commits are still under review. | ||
Are all the Jenkins jobs successfully passed ( Merge-Jobs)? | Yes | https://jenkins.onap.org/view/sdc/job/sdc-master-sdc-merge-java/ https://jenkins.onap.org/view/sdc-jtosca/ https://jenkins.onap.org/view/sdc-sdc-distribution/ https://jenkins.onap.org/view/sdc-sdc-titan/ | ||
Are all binaries available in Nexus? | Yes | |||
Integration and Testing | Have 50 % of System Integration Testing Use Cases been implemented successfully in Jenkins? | |||
Has the project code successfully passed the Daily Build process? | Yes |