Practice AreaCheckpointYes/NoEvidencesHow to?
Architecture


Has the Project team reviewed the APIs with the Architecture Committee (ARC)?YESARC Review

Architecture walkthrough to understand how each project contributes on Release Use Case. ARC to organize the walkthrough.

Is there a plan to address the findings the API review?NALink to planThe plan could be as simple as a Jira issue to track the implementation of findings or a documented plan within the wiki.
Does the team clearly understand that no changes in the API definition is allowed without formal TSC review and approval?YESNAIn the case some changes are necessary, bring the request to the TSC for review and approval.

Is there any changes in the scope, functionalities, deliverable, dependency, resources, API, repositories since M1 milestone?

NOIf Yes, please a link to the evidence of these changes.Critical point to understand is that change is inevitable, and that right timing and clear communication to the community will ease the process of accepting changes.
Provide link to the API Documentation.YES

R2 APIs that are carried forward to R3:

https://onap.readthedocs.io/en/beijing/submodules/dcaegen2.git/docs/sections/apis/deployment-handler.html

https://onap.readthedocs.io/en/beijing/submodules/dcaegen2.git/docs/sections/apis/inventory.html

https://onap.readthedocs.io/en/beijing/submodules/dcaegen2.git/docs/sections/apis/dcaecdap.html

R3 APIs that are new or updated:

https://git.onap.org/dcaegen2/services/prh/tree/swagger.yaml

https://git.onap.org/dcaegen2/collectors/ves/tree/swagger_vescollector_1.3.1.yaml

https://git.onap.org/dcaegen2/platform/configbinding/tree/app/app/swagger.yaml


Release ManagementAre committed Sprint Backlog Stories been marked as "Done" in Jira board?YES

https://jira.onap.org/secure/RapidBoard.jspa?rapidView=49&sprint=677


Are all tasks associated with Sprint Backlog Stories been marked as "Done" in Jira?YEShttps://jira.onap.org/secure/RapidBoard.jspa?rapidView=49&view=planning
Have all findings from previous milestones been addressed?NA



DevelopmentHas the project team reach the Automated Unit Test Code Coverage expectation? (Refer to artifacts available in Sonar)


Guidance on Code Coverage and Static Code Analysis

Tools: Sonar

Is there any pending commit request older than 36 Business hours in Gerrit?YESThey are DRAFTs, or the ones with negative reviews and waiting for contributor response.
Are all the Jenkins jobs successfully passed ( Merge-Jobs)?YEShttps://jenkins.onap.org/view/dcagen2/
Are all binaries available in Nexus?YesYES

Integration and Testing

Have 50 % of System Integration Testing Use Cases been implemented successfully in Jenkins?

YesYES

https://jenkins.onap.org/view/dcagen2/job/dcaegen2-master-verify-csit-prh-testsuites/ (4 cases)

https://jenkins.onap.org/view/dcagen2/job/dcaegen2-master-verify-csit-testsuites/ (12 cases)


Has the project code successfully passed the Daily Build process?YES

https://jenkins.onap.org/view/dcagen2/

Goal is to ensure the latest project commit has not broken the Integration Daily Build