Test No:

TEST-02

Project:

ONAP ESR

Sub Project:

3rd SDNC controller registration

Objective:

support SD-WAN controller registered to ESR-SDNC

Pre-conditions:

1. AC 3rd SD-WAN controller have beed installed

Test step:

  1. Login to ONAP by administrator user.
  2.  In the ONAP esr-sdnc UI, click Register button to Register SDNC information (IP, port, authentication information, etc.) of SDNC manufacturer, click next to fill in the next page, and finally click save button to complete registration.


Test Result:

  1. We can find AC 3rd SD-WAN controller registered in ESR-SDNC portal.

Observation:


...