The milestones are defined at the Release Level and all the supporting project agreed to comply with these dates.
Milestone | Deliverable | Date |
---|---|---|
M0 | Intent to Participate | June 14, 2018 |
M1 | Release Plan M1 Checklist | |
M2 | M2 Checklist | |
M3 | M3 Checklist | |
M4 | M4Checklist | |
RC0 | RC0 Checklist | |
RC1 | RC1Checklist | |
RC2 | RC2 Checklist | |
Signoff | Signoff Checklist |
Team Internal Milestone
This section is optional and may be used to document internal milestones within a project team or multiple project teams. For instance, in the case the team has made agreement with other team to deliver some artifacts on a certain date that are not in the release milestone, it is erecommended to provide these agreements and dates in this section.
...