  1. Pass Portal’s pair wise testing with vid, policy, sdc in SB07 integration env (Farhan? – ETA 4/10).
  2. Fix two CSIT test Jenkin jobs (Sunder – ETA 4/11).
    1. Pending - bringing back the commented test cases - Shireesh (RC1 - 5/3).
      1. Screen maximize issue is failing the test cases - found the fix for screen max issue - waiting to commit changes into gerrit - Sireesh
      2. 26 working/5 more coming right after RC1
      3. Some of the 26 test cases are failing in LF, recheck against VM11
  3. Provide the DB update script with all port changes required for OOM (Sunder/Lorraine? – ETA 4/11). will directly after call
    1. Sunder sent the script to Gary for review - identified that we need help from OOM to execute update sql at deployment time - Sunder to followup with OOM team
    2. JIRA items open for OOM port mapping ANAI, SDK Demo App - Mandeep from OOM Sunder/Manoop
  4. Fix codebase license scan results – remove few libraries/jars (Robert – ETA 4/11).
    1. Robert finished the changes, waiting on Sunder to push the code to gerrit.
  5. Fix high category defect - PORTAL-241 (Hima – ETA 4/12).
  6. Release SDK jars and Docker images (Sunder – ETA 5/3).
    1. sent detail release jars to LF support team
    2. waiting on memory issue fix to release docker images, memory issue caused by Cassandra, memory limit -  Sunder
    3. Followup with Tom Nelson on fix  OOM
  7. Update documentation release notes (Lorraine – ETA 5/3). Done
  8. RC0 checklist is ready - Manoop - ETA - 4/19.
  9. Casablanca goals are being defined here https://wiki.onap.org/display/DW/Casablanca+goals

...

  1. M0 - dev kick-off, Nov 16
  2. M1 - planning Jan 16
  3. M2 Functionality Freeze  →  fill in the contents by Manoop & Leimeng - done
  4. M3 API/Data Model Freeze 
  5. M4 Code Freeze 
  6. RC0 Checklist
  7. RC1 Checklist 
  8. RC2 Checklist 
  9. Release Delivery 

...